Two more smart-meter change orders bring UtiliUse's contract to $28,771,862.79

Change Order No. 3 ($259,553.54, consent agenda, October 28, 2025) added three base station collectors "required to meet the performance standards outlined in the original contract". Change Order No. 4 ($1,942,426.17, 5-0, January 27, 2026) addressed "verified meter quantity shortfalls", converted composite meters to metal-body meters, added radios, expanded installation and restoration, relocated the 24th Street Pump Station monopole and extended project management to the revised schedule. The total award rose from $22,528,581.16 to $28,771,862.79, paid from Texas Water Development Board bond proceeds (CIP #530044).[1][2]