Staff drop the event space from the Thompson pool contract and plan it as a separate project
In October and November 2020 staff worked on a change order to add an event space to the pool project within the budget. On December 16 the director told the Parks Board staff were not recommending adding the event center as a change order at the contractor's quoted price; it would proceed after the summer season as a bid or with City Facilities as general contractor and be ready in 2022.[1][2][3]
What the sources say
- ✓ Verified
The December 16, 2020 minutes record "that we are not recommending the Event Center be added as a change order to the current contract as per the contractor's price quote. Per staff evaluations, this construction project will proceed at the end of the summer season as a bid or utilizing Facilities as the general contractor and would be ready for in 2022." The minutes do not give the quoted price. [3]
- ✓ Verified
No Parks Board minutes read for this site through December 2022 report an award or completion of a separate Thompson Park pool event space. [4]