Staff drop the event space from the Thompson pool contract and plan it as a separate project

In October and November 2020 staff worked on a change order to add an event space to the pool project within the budget. On December 16 the director told the Parks Board staff were not recommending adding the event center as a change order at the contractor's quoted price; it would proceed after the summer season as a bid or with City Facilities as general contractor and be ready in 2022.[1][2][3]