TIRZ #1 board approves a $19,000 arches change order and $1,260 for wayfinding banners, 8-0

Assistant Director of Planning Drew Brassfield said a structural engineer found the anchor bolts at the arches' bases eroded; repairs cost $34,000, and with the $250,000 contract $15,000 under the $265,000 budget, $19,000 more was needed. The board approved Change Order No. 1, 8-0. Beth Duke then presented banners using existing light-pole hardware, printed by Skyrite at about $50 each for $1,260 in all, and the board approved the $1,260, 8-0.[1]