Amarillo MPO transportation plans: the 2025-2050 MTP and the FY 2025-2028 and FY 2027-2030 TIPs (2024-2026)
Quick answers
- What is the latest on Regional transportation plan (MPO)?
- Oct 8, 2026: MPO agenda lists a FY 2027-2030 TIP revision, bylaw changes and a boundary expansion. The agenda for the October 8, 2026 Policy Committee meeting listed resolutions to revise the 2025-2050 MTP and the FY 2027-2030 TIP, "changes to the MPO By-laws and Expansion of the Metropolitan Area Boundary," a resolution supporting the MPO's application to the federal PROTECT grant program, and award of a contract for demographic data for the travel demand model. Read the event
- How far back does this record of Regional transportation plan (MPO) go?
- To Jun 18, 2020: MPO Policy Committee approves a 2020-2045 MTP revision and the draft 2021-2024 TIP. The storyline has 9 dated events in all. Read the event
The Amarillo Metropolitan Planning Organization (MPO) decides which federally funded highway and transit projects in the Amarillo-Canyon area go into its plans. Its Policy Committee, chaired by the Mayor of Amarillo, has 11 voting members from the City of Amarillo, the City of Canyon, Potter and Randall counties, TxDOT's Amarillo District and the Panhandle Regional Planning Commission. The City of Amarillo is its fiscal agent. The committee adopted the FY 2025-2028 Transportation Improvement Program (TIP) on April 11, 2024 and the 2025-2050 Metropolitan Transportation Plan (MTP) on October 17, 2024. The same October meeting added four Loop 335/I-27 interchange Phase II projects to FY 2028. In January 2026 they were listed in FY 2027 and a $49.9 million Loop 335 project at Arden Road was added. The FY 2027-2030 TIP, adopted April 16, 2026, lists $288.3 million in highway construction, all in FY 2027 and all TxDOT-sponsored with no local share. It also lists $21.1 million for Amarillo City Transit over four years, down from $32.7 million in the FY 2025-2028 program.
A storyline groups dated events in order. It is a chronology, not an argument; it does not say why anything happened. All storylines
- Transit & transportation
- Federal & state funds
- Construction & streets
- Leadership & governance
- Budget & taxes
· Precursor
MPO Policy Committee approves a 2020-2045 MTP revision and the draft 2021-2024 TIP
Meeting by Zoom, the Amarillo MPO Policy Committee approved a revision to the 2020-2045 Metropolitan Transportation Plan and the draft 2021-2024 Transportation Improvement Program; the minutes record both votes as 9-0. At the committee's January 16, 2020 meeting, the MPO director said the new TIP projects were funded mostly from TxDOT Categories 2 and 12.[1][2]
- ✓ Verified
The June 18, 2020 minutes record that the committee approved the 2020-2045 MTP revision 9-0 and the draft 2021-2024 TIP 9-0. The minutes list seven voting members present, some of them serving as proxies, and three absent. [1]
- ✓ Verified
At the January 16, 2020 meeting, asked how the new 2021-2024 TIP projects were funded, the MPO director said they were "mostly Category 2, and 12" (TxDOT's metropolitan corridor and strategic priority categories). [2]
· Origin
MPO Policy Committee adopts the FY 2025-2028 Transportation Improvement Program
The MPO Policy Committee adopted the FY 2025-2028 TIP at its quarterly meeting, after a draft was presented on March 21, 2024 and after public meetings and two 30-day comment periods (November 7 to December 10, 2023 and March 18 to April 18, 2024). As adopted, the TIP said there were "currently no individually listed projects" for highways in 2025-2028. Its transit program for Amarillo City Transit totaled $32,734,745 over four years, and it listed City of Amarillo street resurfacing of $2,587,000 a year in local money.[3][4]
- ✓ Verified
The TIP cover gives "Draft TIP presented to MPO Policy Committee: March 21, 2024" and "TIP adopted by MPO Policy Committee: April 11, 2024." Public meetings were held in Amarillo on November 7, 2023 and April 2, 2024 and in Canyon on November 9, 2023 and April 4, 2024. The April 11, 2024 agenda lists "a Resolution to adopt the 2025-2028 Transportation Improvement Plan (TIP)." [3][4]
- ✓ Verified
As adopted, the highway section reads: "Currently no individually listed projects in the 2025-2028 time frame." Highway work appeared only as statewide grouped-project line items (preventive maintenance, bridges, safety, bicycle and pedestrian, and others), with an informational list of grouped projects. [3]
- ✓ Verified
The TxDOT transit financial summary (current as of April 11, 2024) totals $32,734,745 for FY 2025-2028: $18,609,741 federal and $14,125,004 state and other. By year: $7,295,651 (2025), $7,924,428 (2026), $8,376,923 (2027) and $9,137,743 (2028). Almost all of it is FTA Section 5307 urbanized formula money. [3]
- Total
- $32,734,745
- Federal
- $18,609,741
- State other
- $14,125,004
- ✓ Verified
The largest transit line is Amarillo City Transit operating expenses: $4,807,264 in FY 2025 ($2,403,633 federal, $518,225 TxDOT, $1,885,406 local match), rising to $6,226,936 in FY 2028 ($3,199,236 federal, $518,225 TxDOT, $2,509,475 local match). Other yearly lines are preventive maintenance, ADA para-transit service, replacement para-transit vehicles, bus replacements, passenger amenities and training. [3]
- ✓ Verified
Under "Locally Significant Projects," the TIP lists City of Amarillo street resurfacing at $2,587,000 a year in local money for FY 2025 through 2028 (contracts in May each year) and City of Canyon resurfacing at $600,000 a year. The TIP does not say which streets. [3]
- ⚠ Sources differ
The TIP's Amarillo locally funded financial summary gives two four-year totals.
· Related development
MPO Policy Committee approves the 2025-2050 Metropolitan Transportation Plan
The 2025-2050 MTP, the region's long-range plan, was approved by the Policy Board on October 17, 2024. Its financial plan projects $3.7025 billion for construction, $430 million for operations and maintenance and $212 million for transit over 25 years. Its fiscally constrained project list puts the Loop 335/I-27 interchange Phase II projects in 2028 and Loop 335 B-2 Phase V (FM 2186 to 34th Avenue) mostly in 2030. The plan expects the City of Amarillo to spend about $2.6 million a year on local operations and maintenance.[5][6]
- ✓ Verified
The MTP cover reads "Approved by the Policy Board on October 17, 2024" and lists the Mayor of Amarillo as chairman and the Amarillo city manager as vice-chairman. The October 17, 2024 agenda lists "a Resolution adopting the 2025-2050 Metropolitan Transportation Plan." The posted copy's page footers are dated March 26, 2025. [5][6]
- ✓ Verified
The MTP's financial constraint summary projects, over 25 years: construction $3,702,500,000 ($3,672,500,000 federal/state, $30,000,000 local); operations and maintenance $430,000,000 ($350,000,000 federal/state, $80,000,000 local); and transit $212,000,000 ($143,250,000 federal/state, $68,750,000 local). These are projections. The largest category is TxDOT Category 12 Strategic Priority at an average $52,000,000 a year ($1.3 billion over 25 years). The plan says the revenue projections are flat, with no adjustment for inflation, while project costs were inflated 4% a year. [5]
- Construction
- $3,702,500,000
- Operations maintenance
- $430,000,000
- Transit
- $212,000,000
- ✓ Verified
For local money, the MTP projects City of Amarillo local operations and maintenance at an average $2,600,000 a year ($65,000,000 over 25 years) and City of Canyon at $600,000 a year. Local construction by the City of Amarillo and Potter and Randall counties is projected together at $1,200,000 a year ($30,000,000). These are projections. The plan says basic and preventive street maintenance is paid from the City's General Fund and that "in recent years, the City of Amarillo approved certificates of obligation for street and pedestrian improvements." [5]
- ✓ Verified
Exhibit 34 (fiscally constrained project list, YOE total project cost in thousands) lists the Loop 335/I-27 South Interchange Phase II direct connector ramps (A25003) at $229,400,000 for 2028; the Loop 335 third-level main-lane bridge at I-27 (A25002, two phases) at $79,600,000 for 2028; the I-27 frontage road tie-in (A25004) at $36,700,000 for 2028; and Loop 335 B-2 Phase V (A25005), from west of FM 2590 South to south of 34th Avenue, at $264,700,000. Phase III of A25005, north of FM 2186 to north of Arden Road, is listed at $63,600,000 for 2030. [5]
· Related development
TIP revision adds the Loop 335/I-27 interchange Phase II projects and sidewalk and transit-stop projects
At the same meeting, a revision to the FY 2025-2028 TIP (November 2024 revision cycle) added four TxDOT-sponsored Loop 335/I-27 interchange Phase II projects in FY 2028, totaling about $238.3 million in construction with no local share. It also added grouped bicycle, pedestrian and transit-stop projects, including four sponsored by the City of Amarillo, which carry $350,421 in local contributions. Three Loop 335 freeway projects were listed for information only in a new appendix of projects undergoing environmental review, with no costs shown.[3][6]
- ✓ Verified
The October 17, 2024 revision lists four TxDOT-sponsored Loop 335/I-27 Interchange Phase II construction projects as "Add Project" in FY 2028. On the project sheets (revision date 11/2024) the funding totals are $163,127,300 for the two direct connector ramps (A25003-000), $29,113,323 for the third-level bridge segment from I-27 to Bell Street (A25002-001), $27,518,878 for the segment from east of Coulter to I-27 (A25002-000) and $18,572,730 for the I-27 frontage road rehabilitation (A25004-000). That totals $238,332,231 (computed), with $0 local. The sheets' header "YOE cost" boxes differ from these totals by one or two dollars. [3]
- Total
- $238,332,231
- ✓ Verified
The revision also added grouped projects sponsored by the City of Amarillo, each with a local contribution (LC): Business I-40 safety improvements at Amarillo Boulevard and Hughes (A25122-000, FY 2027, Category 7) $722,470 with $144,494 LC; Georgia Street multimodal lanes and crossings (A25092-000, FY 2028, Category 9) $200,517 with $40,103 LC; N. Travis Street sidewalks, Amarillo Boulevard to 18th (A25091-000, FY 2028, Category 7) $627,750 with $125,550 LC; and Amarillo City Transit shelters and bike racks (A25093-000, FY 2028, Category 9) $201,369 with $40,274 LC. Together the four total $1,752,106, with $350,421 in City local contributions (computed). [3]
- Total
- $1,752,106
- City local contribution
- $350,421
- ✓ Verified
TxDOT-sponsored pedestrian projects in Amarillo added in the same revision include Business I-40 from SW 9th Avenue to N. Hughes (A25121-000, FY 2026, Category 7) at $10,189,593 and Business I-40 from N. Hughes to Buchanan (A25120-000, FY 2028) at $2,826,918, both with no local share. W. 3rd Avenue sidewalks, from McMasters to S. Adams (A25090-000, FY 2027, Category 9), is listed at $1,476,462, of which $246,077 is a local contribution; the sheet does not name the contributing entity. [3]
- ✓ Verified
A new Appendix D, "Illustrative Listing of Projects (Projects undergoing Environmental Review)," lists three Loop 335 projects without costs: C-2 from FM 1719 to US 87 and from US 87 to Echo Street (conversion to a four-lane freeway with a third-level interchange at US 87), and D from Echo Street to SE 3rd Avenue. [3]
· Context
MPO adopts its FY 2026 work program and revises the FY 2025 program
The Policy Committee adopted the FY 2026 Unified Planning Work Program, which sets the MPO staff's planning tasks and budget, by Resolution No. 10-7-2025-3. It revised the FY 2025 program by Resolution No. 10-7-2025-2, moving $19,000 among tasks without changing the total. The FY 2025 annual report shows a $480,000 budget and $461,478.55 spent. The same agenda listed an item on a transit representative on the Policy Committee.[7][8][9][10]
- ✓ Verified
Resolution No. 10-7-2025-3 adopts the FY 2026 UPWP "on this the 10th day of July 2025," signed by Cole Stanley as MPO chair. Resolution No. 10-7-2025-2 adopts the revised FY 2025 UPWP the same day. Per the FY 2025 APER, the revision moved $7,000 from subtask 1.1, $7,000 from 2.1 and $5,000 from 4.1 to subtask 3.4 (+$4,000) and 5.1 (+$15,000), with federal approval on September 16, 2025. [7][8][9]
- ✓ Verified
The FY 2025 APER's funding source table shows a $480,000 budget and $461,478.55 spent (96.14%). Task 1.0 (administration) spent $353,571.15 against $344,700 budgeted (102.57%). The APER says the MPO went through its first federal certification review in FY 2025, with no corrective actions assigned. [9]
- Budget
- $480,000
- Expended
- $461,479
· Context
MPO Policy Committee amends its bylaws
The Policy Committee adopted amended bylaws (the sixth version since 2009). They set 11 voting members, based on the 2020 Census. The City of Amarillo has three: the mayor as chair, a council member who represents Amarillo City Transit (appointed by the mayor), and the city manager or a designee as vice chair. The others are the Potter and Randall county judges and one commissioner from each county, the TxDOT Amarillo District Engineer and one district staff member, the Panhandle Regional Planning Commission executive director, and the City of Canyon city manager. The bylaws name the City of Amarillo as fiscal agent. The same agenda listed revisions to the MTP and the FY 2025-2028 TIP.[11][12]
- ✓ Verified
Article II sets representation by population: three representatives for a city over 100,000, one for a city of 10,000-49,999, two each for Potter and Randall counties, one for the Panhandle Regional Planning Commission and two for the TxDOT Amarillo District. Smaller cities are represented by their counties. Non-voting ex officio members are MPO representatives of FHWA and TxDOT, the U.S. representative for the 13th Congressional District, the state senator for District 31 and the state representatives for Districts 86 and 87. A quorum is 51% of voting members, and each member has one vote. [11]
- ✓ Verified
The bylaws make the Policy Committee responsible for reviewing and adopting the TIP and the MTP and their revisions, approving the UPWP, and hiring, supervising, evaluating and terminating the MPO Transportation Planning Director. The Technical Advisory Committee, chaired by the MPO director, recommends plans to it. Article V names the City of Amarillo as fiscal agent, providing staff, salaries and benefits and procurement procedures; program operating costs are reimbursed to the fiscal agent by the State through TxDOT. [11]
- ✓ Verified
The bylaws were "Adopted and approved by the Amarillo Metropolitan Planning Organization Policy Committee on the 9th day of October 2025," signed by Grayson Path as vice chairman and by the MPO director. Earlier versions were adopted January 22, 2009 and amended December 17, 2009, January 16, 2014, October 18, 2018 and January 20, 2022. The October 9, 2025 agenda listed "changes to MPO By-laws" and revisions to the MTP and the FY 2025-2028 TIP. The bylaws say the MPO was designated a Transportation Management Area on June 5, 2023. [11][12]
· Related development
TIP amendment adds the $49.9 million Arden Road project and lists the Loop 335/I-27 projects in FY 2027
The February 2026 revision cycle of the FY 2025-2028 TIP, prepared for the January 8, 2026 Policy Committee meeting, added Loop 335 B-2 Phase V from north of FM 2186 to north of Arden Road (four new main lanes, ramps and an Arden Road grade separation) at $49,920,548 in FY 2027. It listed the four interchange Phase II projects in FY 2027 instead of FY 2028, at the same totals. A transit revision added four FY 2026 Amarillo City Transit projects, including $6.4 million in bus replacements funded from the FTA Section 5339 discretionary program. The agenda for the meeting listed an item on the "Arden Road Bridge Project and Loop 335 Signal Project."[13][14][3][15]
- ✓ Verified
The highway amendment adds Loop 335 B-2 Phase V (CSJ 2635-05-005), north of FM 2186 to north of Arden Road, "Construct 4 new mainlanes, ramps, and Arden Road grade separation," sponsored by TxDOT, at $49,920,548 in FY 2027. That is $18,152,041 from Category 2U (urban corridor) and $31,768,507 from Category 12 (strategic priority), or $39,936,437 federal and $9,984,111 state, with $0 local. [13]
- Total
- $49,920,548
- Federal
- $39,936,437
- State
- $9,984,111
- Local
- $0
- ✓ Verified
The October 2024 revision listed the four Loop 335/I-27 Interchange Phase II projects under FY 2028. The January 2026 amendment lists them under FY 2027 as "Update Project Info," with revision date 02/2026. The ramp project stays at $163,127,300 (Categories 2U, 4 and 12) and the I-27-to-Bell segment at $29,113,323. The amendment does not state why the year changed. [13][3]
- ✓ Verified
The transit amendment adds four FY 2026 Amarillo City Transit projects. Bus replacements (A25T02S(26)): $6,400,000, FTA Section 5339 discretionary, $5,440,000 federal plus $960,000 in transportation development credits. Electric van charging stations (A25T11S(26)): $74,480, $59,200 federal. Software (A25T12S(26)): $390,000, $312,000 federal (Section 5307). Bus stop amenities (A25T05S(26)): $339,577 in TxDOT funds. None shows a local match. [14]
- ✓ Verified
The January 8, 2026 agenda lists "Discuss and Consider Arden Road Bridge Project and Loop 335 Signal Project," resolutions to revise the 2025-2050 MTP and the 2025-2028 TIP, and a presentation of the FY 2025 Annual Performance Expenditure Report. No minutes for the meeting were reviewed, so votes are not recorded here. [15]
· Peak
MPO Policy Committee adopts the FY 2027-2030 TIP and revises the 2025-2050 MTP
The Policy Committee adopted the FY 2027-2030 TIP after a draft was presented at a March 12, 2026 workshop. Its five individually listed highway projects (the four Loop 335/I-27 interchange Phase II projects and the Arden Road segment) total $288,252,779 in FY 2027. That is $230,602,221 federal and $57,650,558 state, with no local share and nothing listed for FY 2028-2030. The transit program totals $21,072,028 over four years, $5,268,007 a year. Compared with the FY 2025-2028 program, the new TIP cuts transit for the overlapping years, drops the replacement para-transit vehicle line and the City's locally funded street resurfacing listing, and shows higher targets for two Business I-40 sidewalk projects. At the same meeting the MTP was revised to add transit safety and security projects.[16][3][17][18][19][20]
- ⚠ Sources differ
The FY 2027-2030 TIP gives two dates for the Policy Committee's adoption meeting.
- Value
- 2026-04-16
Cover ('TIP adopted by MPO Policy Committee: April 16, 2026'); self-certification signed by the Policy Board chair dated 4-16-2026; CivicClerk lists a regular meeting on April 16, 2026 whose agenda includes 'a Resolution to Adopt the 2027-2030 Transportation Improvement Program.'
- ✓ Verified
The FY 2027-2030 TIP individually lists five TxDOT-sponsored Loop 335 construction projects, all in FY 2027 with nothing in FY 2028-2030: the direct connector ramps $163,127,300; the B-2 Phase V Arden Road segment $49,920,548; the third-level bridge segment from I-27 to Bell Street $29,113,323; the segment from east of Coulter to I-27 $27,518,878; and the I-27 frontage road rehabilitation, Sundown Lane to Loop 335, $18,572,730. Funding is $230,602,221 federal and $57,650,558 state, with $0 local match. By category: $50,171,905 Category 2 (metropolitan and urban corridor), $16,779,000 Category 4 (statewide connectivity) and Category 12 (strategic priority) for the rest. [16]
- Total
- $288,252,779
- Federal
- $230,602,221
- State
- $57,650,558
- Local
- $0
- ⚠ Sources differ
The FY 2027-2030 TIP financial summary gives the FY 2027 highway total two ways.
Reported value 1[16]
- Fy2027 highway
- $288,252,779
- Category 12
- $211,301,874
'Authorized FY 2027' column and the Category 1-12 funding source breakdown ($230,602,221 federal + $57,650,558 state); this equals the sum of the five project sheets.
Reported value 2[16]
- Fy2027 highway
- $288,252,689
- Category 12
- $211,301,784
'Programmed FY 2027' column and 'Total Programmed FY 2027-2030' column of the same table, where the Category 12 entry reads $211,301,784.
- ✓ Verified
The FY 2027-2030 transit financial summary (current as of 2/26/2026) shows $5,268,007 a year: $4,790,934 Section 5307, $255,000 Section 5310 and $222,073 other FTA (Section 5339 bus replacement). The four-year total is $21,072,028 ($12,594,736 federal, $8,477,292 state and other). Each year lists operating expenses $3,700,458 ($1,850,230 federal, $377,787 TxDOT, $1,472,441 local match), preventive maintenance $802,297, ADA paratransit $274,456, passenger amenities $255,000, bus replacements $222,073 and training $13,723. [16]
- Total
- $21,072,028
- Federal
- $12,594,736
- State other
- $8,477,292
- ✓ Verified
The local match on the FY 2027-2030 transit sheets totals $1,741,536 a year (computed). That is operating $1,472,441, preventive maintenance $160,459, ADA paratransit $54,891, passenger amenities $51,000 and training $2,745; bus replacements show none. The sheets list Amarillo City Transit as sponsor and do not say what source supplies the local match. [16]
- Local match per year
- $1,741,536
- ✓ Verified
For the two years both programs cover, the FY 2027-2030 TIP lists less transit money than the FY 2025-2028 TIP. FY 2027 falls from $8,376,923 to $5,268,007 and FY 2028 from $9,137,743 to $5,268,007. Operating expenses for FY 2028 fall from $6,226,936 (local match $2,509,475) to $3,700,458 (local match $1,472,441). The FY 2025-2028 "Replace Para-Transit Vehicle" line ($471,900 in FY 2027 and $519,090 in FY 2028) does not appear in the FY 2027-2030 listing, which adds a Section 5310 passenger-amenities line. Neither document states a reason for the changes. [3][16]
- ✓ Verified
The FY 2025-2028 TIP had a "Locally Significant Projects" section listing City of Amarillo street resurfacing at $2,587,000 a year in local money. The FY 2027-2030 TIP's table of contents and tables have no locally funded project section, and no City of Amarillo resurfacing line appears in it. [3][16]
- ✓ Verified
Exhibit A of the FY 2027-2030 TIP, a list of grouped projects "for informational purposes only" with construction target amounts, lists some of the 2024 pedestrian projects at different amounts and years. Business I-40 from SW 9th Avenue to Hughes (CSJ 0090-06-049) is listed at $16,500,000 in FY 2027 (June); the FY 2025-2028 TIP listed it at $10,189,593 for FY 2026. Business I-40 from N. Hughes to Buchanan (0090-06-050) is $6,877,269 in FY 2028, against $2,826,918 before. Travis Street from Business I-40 to 18th (0904-02-057) is $500,000 in FY 2028, against $627,750 before. Exhibit A also lists an "Amarillo Safe Streets for All pedestrian enhancements" item (0904-00-245) at $1,072,114 in FY 2027. [16][3]
- ⚠ Sources differ
The MTP and the TIPs give different costs for the same Loop 335 projects; they measure different things.
Reported value 1[5]
- A25003
- $229,400,000
- A25002
- $79,600,000
- A25004
- $36,700,000
- Arden segment
- $63,600,000
2025-2050 MTP Exhibit 34, YOE 'total project cost', which the plan says includes engineering, right-of-way, utilities and construction; timing 2028 (2030 for the Arden segment).
Reported value 2[16]
- A25003
- $163,127,300
- A25002
- $56,632,201
- A25004
- $18,572,730
- Arden segment
- $49,920,548
FY 2027-2030 TIP project sheets, authorized construction funding (A25002 = $29,113,323 + $27,518,878, computed); all in FY 2027.
- ✓ Verified
The May 2026 MTP revision, dated for the April 16, 2026 Policy Committee meeting, adds two transit projects, Safety Enhancements (A25T13S) and Security Enhancements (A25T14S), with no roadway changes. Its Transit Short Range Plan 2025-2035 totals $85,466,000, led by operating expense ($44,451,000), ADA para-transit service ($20,264,000) and preventive maintenance ($9,860,000). [17]
- Transit short range plan
- $85,466,000
- ✓ Verified
The FY 2025 annual listing of obligated projects reports $3,196,107 in federal transit funds obligated in FY 2025. For operating expenses it shows $2,191,376 federal, $419,763 state and $1,771,677 local ($4,382,766 total as printed; the three parts add to $4,382,816). The FY 2025-2028 TIP had programmed $4,807,264 for that line, including a $1,885,406 local match. [21][3]
- ✓ Verified
None of the MPO documents reviewed states why the Loop 335/I-27 projects moved from FY 2028 to FY 2027, why the transit amounts fell, or why the City's locally funded resurfacing line was not carried into the FY 2027-2030 TIP. Minutes of the 2024-2026 Policy Committee meetings were not available on CivicClerk. [16][13][20]
· Context
MPO agenda lists a FY 2027-2030 TIP revision, bylaw changes and a boundary expansion
The agenda for the October 8, 2026 Policy Committee meeting listed resolutions to revise the 2025-2050 MTP and the FY 2027-2030 TIP, "changes to the MPO By-laws and Expansion of the Metropolitan Area Boundary," a resolution supporting the MPO's application to the federal PROTECT grant program, and award of a contract for demographic data for the travel demand model. Minutes recording the outcome were not posted as of October 22, 2026.[22][23][20]
- ✓ Verified
The October 8, 2026 agenda lists items 4.A (revision to the 2025-2050 MTP), 4.B (revision to the 2027-2030 TIP), 4.C ("changes to the MPO By-laws and Expansion of the Metropolitan Area Boundary"), 4.D (FY26 project priority list), 4.E (FY 2027-2037 10-year plan), 4.F (support for the MPO's application to the PROTECT grant program) and 4.G (award of the RFQ contract for demographics for the travel demand model). The September 10, 2026 workshop agenda listed a presentation on updating the Metropolitan Area Boundary and bylaws. [22][23]
Related storylines: Amarillo City Transit: the coordinated transportation plan, route review and 2026 federal grants (2025-2026)Amarillo's certificates of obligation (2017-2026)