Ask AI
Opens the assistant with a question about this page. Answers come from the AI, not this site.
ChatGPTClaudePerplexity· Context
Board awards $198,507 to demolish the old baseball stadium at the Tri-State Fairgrounds
Against $805,000 the board had previously approved, it awarded demolition and abatement of the baseball field at the Tri-State Fairgrounds to Lloyd Nabors (Lot 1, $175,000) and Arlo Environmental (Lot 2, $23,507), and moved the remaining $606,493 to a new line for fencing and grounds maintenance at the fairgrounds. By August 2023 the stadium had been demolished and the site was being fenced and turned into parking.[1][2]
What the sources say
- ✓ Verified
Storrs said the board had previously approved $805,000 for the demolition and abatement of the baseball field at the Tri-State Fairgrounds. The highest evaluated bidders were Lloyd Nabors (Lot 1, $175,000.00) and Arlo Environmental (Lot 2, $23,507.00), a total award of $198,507.00, approved unanimously. On a separate motion the board moved "the total remaining budget of $606,493 to a new line item for fencing and grounds maintenance." [1]
- Approved budget
- $805,000
- Award
- $198,507
- Reallocated
- $606,493
- ✓ Verified
On August 21, 2023 Tri-State Exposition general manager Brady Ragland said the stadium had been demolished and the Exposition was adding fencing around the site and creating a parking surface. [2]