Northeast Interceptor reaches substantial completion (May 2026)

A June 9, 2026 staff memo says the Northeast Interceptor "reached substantial completion in May 2026," against the summer 2025 completion the October 2023 award memo had anticipated. The City's check register records $67,740,350.46 in payments to S.J. Louis Construction of Texas from March 2024 to February 2026; the register does not tie payments to projects.[1][2]