Northeast Interceptor reaches substantial completion (May 2026)
A June 9, 2026 staff memo says the Northeast Interceptor "reached substantial completion in May 2026," against the summer 2025 completion the October 2023 award memo had anticipated. The City's check register records $67,740,350.46 in payments to S.J. Louis Construction of Texas from March 2024 to February 2026; the register does not tie payments to projects.[1][2]
S.J. Louis Construction of Texas, Ltd.
What the sources say
- ✓ Verified
The City's check register records $67,740,350.46 in 23 payments to S.J. Louis Construction of Texas between 2024-03-07 and 2026-02-17 (FY2024 $42,016,134.03; FY2025 $24,829,124.86; FY2026 $895,091.57). The register does not identify the project each payment funded. In the council minutes reviewed (2021-2026), S.J. Louis appears only in Northeast Interceptor items. [2]
- Total
- $67,740,350
- Payments
- 23
- ✓ Verified
The June 2026 memo does not state a final construction cost, a final acceptance or closeout of the S.J. Louis contract, or whether the Imhoff tank and lift station have been taken out of service, and no other City record found states them. [1]