Ask AI
Opens the assistant with a question about this page. Answers come from the AI, not this site.
ChatGPTClaudePerplexityStoryline · 16 events · Feb 23, 2021 – Jun 9, 2026
Northeast Interceptor sewer line (2021-2026)
Quick answers
- What is the latest on Northeast Interceptor?
- Jun 9, 2026: Council approves $95,000 Kimley-Horn amendment for construction-phase services through May 2026. On June 9, 2026 the council approved, 5-0 on the consent agenda, Amendment No. 3 to the Kimley-Horn agreement for $95,000, bringing it to $5,441,800, for a project representative and materials testing from January through May 2026, funded from water and sewer revenue bonds (CIP No. 530042). Read the event
- How far back does this record of Northeast Interceptor go?
- To Feb 23, 2021: Council approves $5,248,300 Kimley-Horn agreement to design the Northeast Interceptor. The storyline has 16 dated events in all. Read the event
Phase 1 of the Northeast Interceptor, about 13 miles of gravity sewer main carrying northeast Amarillo wastewater to the River Road Wastewater Treatment Plant, was built under a $71,266,760.15 contract awarded in October 2023 (later $72,862,527.80) and reached substantial completion in May 2026. Phase 1 also took an Imhoff tank and a lift station out of service; City staff said it would move about 1 million gallons per day off the overloaded collection system that feeds the Hollywood Road plant. The council hired Kimley-Horn to design it in February 2021 ($5,248,300, later amended to $5,441,800) and approved easement and surface-damage agreements with landowners in 2022 and 2023. Two bids were opened on September 14, 2023. On October 24, 2023 the council awarded Phase 1 to S.J. Louis Construction of Texas, with $23,826,635.15 to come from revenue bonds still to be issued. On December 12, 2023 it authorized the New Series 2024 water and sewer revenue bonds ($19,300,000 issued), which the staff memo tied to the interceptor, and in January 2024 approved an AEDC agreement to pay half that debt service. Two change orders brought the contract to its final amount; a June 2026 staff memo reports the substantial completion.
A storyline groups dated events in order. It is a chronology, not an argument; it does not say why anything happened. All storylines
- Water & sewer
- Votes & elections
- Construction & streets
- Debt & financing
- Downtown & development
- Contracts & procurement
Where the story starts depends on the framing
- From the Kimley-Horn design and construction-phase services agreement (February 2021): starts with Council approves $5,248,300 Kimley-Horn agreement to design the Northeast Interceptor (Feb 23, 2021)
- From the bids and the Phase 1 construction award (September-October 2023): starts with Council awards $71,266,760.15 Phase 1 construction contract to S.J. Louis Construction of Texas (Oct 24, 2023)
· Origin
Council approves $5,248,300 Kimley-Horn agreement to design the Northeast Interceptor
On February 23, 2021 the council approved, 5-0 on the consent agenda, a $5,248,300 professional engineering services agreement with Kimley-Horn and Associates for the planning, design, procurement and construction phases of the northeast wastewater interceptor line. The agenda description said the line was essential for future growth, including the future expansion of Centerport, and would serve or relieve underserved areas on the east side of the City.[1][2]
Ginger NelsonElaine HaysFreda PowellEddy SauerHoward SmithKimley-Horn and Associates
- ✓ Verified
On February 23, 2021 the council approved on its consent agenda, 5-0 (Mayor Nelson and Councilmembers Hays, Powell, Sauer and Smith), a professional engineering services agreement with Kimley-Horn and Associates for $5,248,300.00 for "the planning, design, procurement, and construction services phases of the northeast wastewater interceptor line." The item said the line was "essential for future City growth and economic development including the future expansion of Centerport," with the primary purpose to "serve or provide relief in underserved areas of the east side of the City." [1]
- Amount
- $5,248,300
- ✓ Verified
A January 2024 amendment describes the Kimley-Horn agreement as dated February 24, 2021, for design and construction services for about 80,000 linear feet of sanitary sewer mains in Potter County, and says funding for the project was approved in the FY 16/17 through FY 20/21 Community Investment Program. [2]
- ✓ Verified
The two CIP editions that list the interceptor describe it differently. The FY2020/21 edition calls it "a multi-year pipeline project to help eliminate strain on the wastewater collection system" that would "open up gravity flows on the Northeast side of Amarillo and potentially eliminate the need for future lift stations and the Imhoff tank." The FY2022/23 edition says it "will run from I-40 north to the RR WRF" (River Road Water Reclamation Facility) and "will Move water currently going to HR WRF [Hollywood Road] to RR WRF." [3][4]
· Related development
Council approves four easement and surface-damage agreements for the Northeast Interceptor ($741,400)
On December 13, 2022 the council approved, 5-0 on the consent agenda, four permanent easement and surface damage and restoration agreements with private landowners, for $211,400, $200,000, $230,000 and $100,000, each "to facilitate the construction of a wastewater pipeline associated with the Northeast Interceptor project."[5]
Ginger NelsonFreda PowellEddy SauerHoward SmithCole Stanley
- ✓ Verified
On December 13, 2022 the council's consent agenda, approved 5-0 (Mayor Nelson, Mayor Pro Tem Powell, and Councilmembers Sauer, Smith and Stanley), included four permanent easement and surface damage and restoration agreements with private landowners for $211,400.00, $200,000.00, $230,000.00 and $100,000.00, each to facilitate construction of a wastewater pipeline associated with the Northeast Interceptor project. The four total $741,400. [5]
- Total
- $741,400
· Related development
Council approves three more easement agreements for the Northeast Interceptor (January-July 2023)
The council approved further land agreements for the interceptor: a $289,550 permanent easement and surface damage agreement with private landowners (January 10, 2023, consent agenda, 5-0), a $175,000 surface damage and restoration agreement with a family trust and co-owners (March 28, 2023, consent agenda, 5-0), and a $55,000 temporary construction easement, sanitary sewer line easement and surface damage agreement with CVMR (Texas) Inc. (July 11, 2023, 5-0).[6][7][8]
Ginger NelsonFreda PowellEddy SauerHoward SmithCole StanleyJosh CraftDon TippsTom ScherlenLes SimpsonCVMR (Texas) Inc.
- ✓ Verified
The January 10, 2023 consent agenda, approved 5-0, included a $289,550.00 permanent easement and surface damage and restoration agreement with private landowners to facilitate construction of a wastewater pipeline associated with the Northeast Interceptor project. [6]
- Amount
- $289,550
- ✓ Verified
The March 28, 2023 consent agenda, approved 5-0, included a "Northeast Interceptor - Surface Damage Agreement," a surface damage and restoration agreement with a family trust and co-owners for $175,000.00. [7]
- Amount
- $175,000
- ✓ Verified
On July 11, 2023 the council voted 5-0 (Stanley, Craft, Tipps, Scherlen, Simpson; motion by Don Tipps, second by Les Simpson) to approve a temporary construction easement, a sanitary sewer line easement and a surface damage and restoration agreement with CVMR (Texas) Inc. for $55,000.00 for the Northeast Interceptor. [8]
- Amount
- $55,000
- ✓ Verified
The seven easement and surface-damage agreements for the Northeast Interceptor found in council minutes from December 2022 to July 2023 total $1,260,950. Other land agreements may have been approved in meetings not reviewed. [5][6][7][8]
- Total
- $1,260,950
· Related development
Two bids received for Phase 1 of the Northeast Interceptor
Bid No. 7683, a best-value bid for the Amarillo Northeast Interceptor, opened at 4:00 p.m. on September 14, 2023. S.J. Louis Construction of Texas (San Antonio) bid $71,266,760.15 and Harper Bros Construction (Houston) bid $84,483,281.00.[9]
S.J. Louis Construction of Texas, Ltd.
- ✓ Verified
The tabulation for Bid No. 7683 ("BVB for wastewater collection improvements: Amarillo Northeast Interceptor"), opened 4:00 p.m. September 14, 2023 and awarded as one lot, lists two bids: Harper Bros Construction of Houston at $84,483,281.00 and S.J. Louis Construction of Texas of San Antonio at $71,266,760.15. [9]
- Low bid
- $71,266,760
- High bid
- $84,483,281
· Related development
Council discusses the Northeast Interceptor bids and how to pay for the shortfall
The September 26, 2023 agenda included "Discuss Northeast Interceptor Construction Project." A later staff memo says council was presented information that day about the project, the bids received and potential funding sources, including a proposed water and sewer revenue bond issue, "for the additional amount needed." The minutes record no action on the item.[10][11]
Cole StanleyJosh CraftDon TippsTom ScherlenLes Simpson
- ✓ Verified
The December 12, 2023 staff memo for Ordinance No. 8101 states: "At the September 26, 2023 City Council meeting, Council was presented information about the NE interceptor construction project, the bids received for the project, and potential funding sources, including this proposed debt issuance, for the additional amount needed." [11]
- ✓ Verified
The September 26, 2023 minutes list item 8.F, "Discuss Northeast Interceptor Construction Project," among discussion items and record no vote on it. The agenda packet for that meeting contains no presentation material for the item, so the figures shown that day are not in the public record reviewed. [10][12]
· Peak
Council awards $71,266,760.15 Phase 1 construction contract to S.J. Louis Construction of Texas
On October 24, 2023 the council voted 5-0 to award the Phase 1 construction contract to S.J. Louis Construction of Texas for $71,266,760.15: about 13 miles of sanitary sewer pipe and the abandonment of an Imhoff tank and a lift station in the northeast basin. The memo funded it with $47,440,125.00 in water and sewer revenues already budgeted and $23,826,635.15 from revenue bonds still to be issued, with utility capital funds covering the full amount until then. It anticipated completion in summer 2025.[13][9][14]
Cole StanleyJosh CraftDon TippsTom ScherlenLes SimpsonFloyd HartmanS.J. Louis Construction of Texas, Ltd.
- ✓ Verified
On October 24, 2023 the council voted 5-0 (Stanley, Craft, Tipps, Scherlen, Simpson; motion by Don Tipps, second by Josh Craft) to award S.J. Louis Construction of Texas, Ltd. a $71,266,760.15 construction contract for Phase 1 of the Amarillo Northeast Sanitary Sewer Interceptor project. Assistant City Manager Floyd Hartman presented the item. [13]
- Amount
- $71,266,760
- ✓ Verified
Phase 1 consists of about 13 miles of sanitary sewer pipe and the abandonment of an Imhoff tank and a lift station in the northeast basin. The memo says the lift station being abandoned serves the prison and nearby industrial park and pumps about 1 million gallons per day, which is pumped five more times before reaching the Hollywood Road plant; that previous studies showed this system to be overloaded per TCEQ requirements; and that the interceptor would move that flow by gravity to the River Road plant. It says the interceptor was a high-priority need in the 2012 Wastewater Master Plan and the Northeast Basin Study, and lists added service to the Centerport industrial area, growth and reduced pumping as long-term benefits. [9]
- ✓ Verified
The award memo funded the contract with $47,440,125.00 available in project budget 530042 (water and sewer revenues) and $23,826,635.15 to be obtained through water and sewer revenue bonds, and said FY 23/24 utilities capital project funds would secure the full amount until the bonds were issued. [13][9]
- Cash funded
- $47,440,125
- Bond funded
- $23,826,635
- ✓ Verified
Assistant City Manager Floyd Hartman; Councilmember Les Simpson (as reported by NewsChannel10): Assistant City Manager Floyd Hartman told NewsChannel10 that the top end of the line "starts at Highway 60 out north by the airport" and that "it doesn't just impact the area where it's at, it impacts the entire city because it provides additional services." Councilmember Les Simpson called it "a much needed investment in our city's infrastructure," referring to it as the "Northwest Interceptor." [14]
- ✓ Verified
The City's five-year Community Investment Program (CIP) gave an estimated capital expenditure of $25,226,000 for the Northeast Interceptor in the FY2020/21 edition (project 523203, "WWC North-East Interceptor," all in FY2020/21; PDF p. 114) and $26,170,825 in the FY2022/23 edition (project 530042, "NE Interceptor," all in FY2022/23; PDF p. 130), both from the Water and Sewer System Fund. The FY2021/22 edition has no Northeast Interceptor project page or summary line, and the FY2023/24 edition (dated November 2023) does not list the project. The Phase 1 construction contract the council awarded on October 24, 2023 was $71,266,760.15, about 2.7 times the FY2022/23 estimate. The CIP editions do not explain the difference. [3][15][4][16][13]
- Cip fy2020 21 edition
- $25,226,000
- Cip fy2022 23 edition
- $26,170,825
- Phase1 award
- $71,266,760
- ✓ Verified
The FY2022/23 CIP says the year-one program approved through the 2022/2023 budget included $57.8 million of debt, $46.5 million of it water and sewer utility bond proceeds, and that "the bulk of the water and sewer utility bonds are encompassed by three projects; the Northeast Interceptor Sewer line for $26.2 Million, the Water Rights Expansion project for $18 Million, and the Arroyo Outfall sewer line ... for $2.3 Million." [4]
- Year one debt
- $57,800,000
- Water sewer bond proceeds
- $46,500,000
- Interceptor
- $26,200,000
· Related development
Interim City Manager asks the AEDC board to take part in the Northeast Interceptor project
Interim City Manager Andrew Freeman "presented an opportunity for AEDC to participate in the Northeast Interceptor construction project." The minutes record no action on the item.[17]
Andrew FreemanKevin CarterAmarillo Economic Development Corporation (AEDC)
· Related development
Council authorizes water and sewer revenue bonds, New Series 2024 (Ord. 8101), tied to the interceptor
On December 12, 2023 the council adopted, 5-0, Ordinance No. 8101 authorizing Waterworks and Sewer System Revenue Bonds, New Series 2024. The staff memo put proceeds at about $20 million and pointed to the September 26 presentation of the Northeast Interceptor bids and funding sources. City financial reports record $19,300,000 issued, dated December 1, 2023, maturing through 2053. The City's debt schedules list the full $19,300,000 as unspent at September 30, 2024 and 2025.[18][11][19][20][21]
Cole StanleyJosh CraftDon TippsTom ScherlenLes SimpsonLaura Storrs
- ✓ Verified
On December 12, 2023 the council adopted Ordinance No. 8101 authorizing Waterworks and Sewer System Revenue Bonds, New Series 2024, 5-0 (Stanley, Craft, Tipps, Scherlen, Simpson; motion by Josh Craft, second by Tom Scherlen). [18]
- ✓ Verified
The staff memo from Interim Deputy City Manager and CFO Laura Storrs said "the approximately $20 million in proceeds will be used to improve and extend the City's waterworks and sewer system," repaid from the system's net revenues, and cited the September 26, 2023 presentation of the NE interceptor bids and funding sources "for the additional amount needed." [11]
- Proceeds estimate
- $20,000,000
- ✓ Verified
The City's FY2025 financial report says the City issued the Series 2024 water and sewer revenue bonds on December 1, 2023 in the amount of $19,300,000, at rates of 4.00% to 6.00%, maturing annually through 2053. The September 30, 2025 debt schedule lists $19,175,000 outstanding and $14,500,564 in remaining interest. [19][21]
- Issued
- $19,300,000
- Outstanding sep 2025
- $19,175,000
- ✓ Verified
The City's debt schedules list none of the $19,300,000 Series 2024 proceeds as spent and all of it as unspent at both September 30, 2024 and September 30, 2025, while staff memos in 2024 and 2026 describe the interceptor as funded in part from water and sewer revenue bonds. The City has not publicly reconciled the two. [20][21][22][23]
- Unspent sep 2025
- $19,300,000
· Related development
AEDC board approves $10 million toward Northeast Interceptor debt service, 5-0
After an executive session, Director Brown moved to approve the City's request for AEDC cost participation in the Northeast Interceptor project "in the amount of $10,000,000 to be paid out in a term not to exceed 30 years and not more than 50% of the City's debt service payment as it relates to the bond indebtedness." Vice-Chair Meander seconded and it was approved unanimously.[24]
Kevin CarterAmarillo Economic Development Corporation (AEDC)
- ⚠ Sources differ
The AEDC's commitment to the interceptor is stated differently in its board minutes and its own project report.
Reported value 1[24]
- Commitment
- $10,000,000
AEDC board, December 18, 2023: $10,000,000, paid over no more than 30 years and not more than 50% of the City's debt service payment.
Reported value 2[25]
- Original project
- $17,440,050
- Paid prior years
- $319,952
- Paid ytd
- $163,500
AEDC cumulative project status report through January 31, 2025: 'North East Interceptor Participation' with an original project amount of $17,440,050, $319,952 paid in prior years, $163,500 paid year to date and $16,518,596 in future commitments. The report does not explain the difference from the $10,000,000 in the board motion.
· Context
Council approves $58,500 Kimley-Horn amendment splitting out Phase 2 of the interceptor
On January 23, 2024 the council approved, 5-0 on the consent agenda, Amendment No. 2 to the Kimley-Horn agreement ($58,500, bringing it to $5,346,800) to prepare a separate plan set for Northeast Interceptor Phase 2 and assess the bridge over East Amarillo Creek leading to the River Road plant. Phase 2 was described as about 4,118 feet of 12-inch force main and 12,743 feet of 36-inch gravity sewer with two BNSF and two TxDOT crossings.[28][2]
Cole StanleyJosh CraftDon TippsTom ScherlenLes SimpsonKimley-Horn and Associates
- ✓ Verified
Amendment No. 2 added $58,500 to the Kimley-Horn agreement (original $5,248,300; Amendment No. 1 $40,000; amended total $5,346,800) to separate Northeast Interceptor Phase 2 into its own plan set and to determine the load rating of the bridge over East Amarillo Creek leading to the River Road plant, which would be used to access the project. It was approved on the January 23, 2024 consent agenda, 5-0, funded from water and sewer revenue bonds. [28][2]
- Amendment
- $58,500
- Revised total
- $5,346,800
- ✓ Verified
The amendment scope describes NEI Phase 2 as about 4,118 linear feet of 12-inch HDPE force main and about 12,743 linear feet of 36-inch FRP gravity sewer, with two BNSF railroad crossings and two TxDOT crossings; the October 2023 layout map labels Phase 2 as the "Lift Station 38 re-route." No council record of a Phase 2 construction award was found. [2][9]
· Related development
Change Order No. 2 adds $1,406,065.95 for longer tunnels and alignment changes
On June 11, 2024 the council approved, 5-0, Change Order No. 2 with S.J. Louis Construction of Texas for $1,406,065.95, raising the contract to $72,672,826.10. It extended tunneling at eight utility crossings, including 607 more feet of 72-inch tunnel at depths of 50 to 70 feet, and adjusted the alignment for site conditions the memo described as unknown.[29][22]
Cole StanleyJosh CraftDon TippsTom ScherlenLes SimpsonS.J. Louis Construction of Texas, Ltd.
- ✓ Verified
Change Order No. 2 ($1,406,065.95) raised the S.J. Louis contract from $71,266,760.15 to $72,672,826.10, adding 607 linear feet of 72-inch tunnel extensions at depths of 50 to 70 feet, modifying two manholes, replacing a water service line and adding 8 calendar days, to address "unknown conditions the contractor is encountering on-site." The council approved it 5-0 on June 11, 2024 (motion by Don Tipps, second by Josh Craft). [29][22]
- Change order
- $1,406,066
- Revised contract
- $72,672,826
· Related development
Change Order No. 3 adds $189,701.70 for unmapped utility conflicts
On December 10, 2024 the council approved, 5-0 on the consent agenda, Change Order No. 3 for $189,701.70, bringing the S.J. Louis contract to $72,862,527.80 and adding 42 calendar days. It covered relocating a power pole and service meter, rerouting and replacing private gas service lines on two properties, and auger boring under two gas lines not shown in utility records, so an 18-inch line could carry flow from the Imhoff tank to the interceptor.[30][31]
Cole StanleyJosh CraftDon TippsTom ScherlenLes SimpsonMichael PriceS.J. Louis Construction of Texas, Ltd.
- ✓ Verified
Change Order No. 3 ($189,701.70) raised the contract to $72,862,527.80 and added 42 calendar days. The memo said the conflicts "were unknown by the City and its contractor at the time of bidding" and that staff was "seeking possible mechanisms for City reimbursement of some or all of these expenses." The council approved it on the December 10, 2024 consent agenda, 5-0. [30][31]
- Change order
- $189,702
- Revised contract
- $72,862,528
· Context
Council receives a Northeast Interceptor project update
The August 26, 2025 regular meeting included a "Northeast Interceptor project update" presented by Floyd Hartman. The minutes record no details of the update and no action.[32]
- ✓ Verified
The August 26, 2025 minutes record item 8.C, "Northease Interceptor project update" (sic): "Mayor Stanley introduced the item. Mr. Hartman presented the item." No figures or schedule are recorded. [32]
· Resolution
Northeast Interceptor reaches substantial completion (May 2026)
A June 9, 2026 staff memo says the Northeast Interceptor "reached substantial completion in May 2026," against the summer 2025 completion the October 2023 award memo had anticipated. The City's check register records $67,740,350.46 in payments to S.J. Louis Construction of Texas from March 2024 to February 2026; the register does not tie payments to projects.[23][33]
S.J. Louis Construction of Texas, Ltd.
- ✓ Verified
The City's check register records $67,740,350.46 in 23 payments to S.J. Louis Construction of Texas between 2024-03-07 and 2026-02-17 (FY2024 $42,016,134.03; FY2025 $24,829,124.86; FY2026 $895,091.57). The register does not identify the project each payment funded. In the council minutes reviewed (2021-2026), S.J. Louis appears only in Northeast Interceptor items. [33]
- Total
- $67,740,350
- Payments
- 23
- ✓ Verified
The June 2026 memo does not state a final construction cost, a final acceptance or closeout of the S.J. Louis contract, or whether the Imhoff tank and lift station have been taken out of service, and no other City record found states them. [23]
· Context
Council approves $95,000 Kimley-Horn amendment for construction-phase services through May 2026
On June 9, 2026 the council approved, 5-0 on the consent agenda, Amendment No. 3 to the Kimley-Horn agreement for $95,000, bringing it to $5,441,800, for a project representative and materials testing from January through May 2026, funded from water and sewer revenue bonds (CIP No. 530042).[34][23]
Cole StanleyTim ReidDon TippsDavid PrescottLes SimpsonJerry DanforthKimley-Horn and Associates
- ✓ Verified
Amendment No. 3 added $95,000 to the Kimley-Horn agreement (original $5,248,300; previous amendments $98,500; revised total $5,441,800) for construction-phase services from January through May 2026, a project representative and construction materials testing, funded from water and sewer revenue bonds (CIP No. 530042). It was approved on the June 9, 2026 consent agenda, 5-0. [23][34]
- Amendment
- $95,000
- Revised total
- $5,441,800