Council adds $4.97 million Grant Street drainage work to the City Hall construction contract, 5-0
The council approved adding drainage infrastructure from City Hall to the north side of 3rd Avenue along Grant Street to the City Hall construction contract with Western Builders of Amarillo, Inc., for $4,967,536.00 from the Drainage Utility Fund. The item was pulled from the consent agenda and approved 5-0.[1]
Cole StanleyJosh CraftDon TippsTom ScherlenLes SimpsonDonny HooperJerry DanforthWestern Builders of Amarillo
What the sources say
- ✓ Verified
Item 8.U on May 28, 2024 proposed adding to the "current City Hall construction contract" drainage infrastructure from City Hall to the north side of 3rd Avenue along Grant Street, with earthwork and concrete paving. The item said adding the work let the general contractor finish it before City Hall opened and that "utilizing the existing CMAR contract has allowed the city to negotiate pricing effectively." The award was to Western Builders of Amarillo, Inc. for $4,967,536.00 from the Drainage Utility Fund, budgeted. [1]
- Amount
- $4,967,536
- ✓ Verified
Councilmember Tom Scherlen asked that item 8.U be pulled from the consent agenda. After a presentation by Managing Director of Public Works Donny Hooper and Jerry Danforth, the council approved it 5-0 (Mayor Cole Stanley and Councilmembers Josh Craft, Don Tipps, Tom Scherlen and Les Simpson). [1]