Deadline for Texas Tech's notice to proceed and Fermi's $9 million lease escrow

Pending Scheduled; has not yet occurred.

Under the ground lease as described in Fermi's filings, Fermi must receive a notice to proceed from the Texas Tech University System by December 31, 2026 before vertical data-center construction, or the System may terminate the lease. The notice is conditioned on, among other things, a Phase 1 tenant lease of at least 200 MW and Phase 1 financing. The $9 million escrow under the collaboration agreement is also due by that date.[1][2]

Texas Tech University SystemFermi America (Fermi, Inc.)