Council approves a $320,000 transfer and $319,260 HDR design contract for Lift Station 19

The October 13, 2026 council agenda lists a $320,000 transfer from the Wastewater System Improvements & Repairs capital project to a new Lift Station 19 Relocation Design project, and a $319,260 professional services contract with HDR Engineering for a Phase 1 alternatives evaluation and preliminary design of a Lift Station 19 replacement, including evaluating consolidation of Lift Stations 16 and 25.[1][2][3]

Jerry DanforthHDR Engineering, Inc.