Halff Associates hired to design the Playa 7 pump station ($2,425,000)
On the consent agenda approved 5-0, the council awarded Halff Associates $2,425,000 for design and construction services for a Playa 7 pump station and a force main down Soncy Road to West Amarillo Creek, from drainage bond proceeds. An August 25, 2026 amendment ($393,812) raised it to $2,818,812 after the force main route was moved next to Soncy Road.[1][2]
Jerry DanforthHalff Associates, Inc.
What the sources say
- ✓ Verified
On August 26, 2025 the council approved, 5-0 on its consent agenda, a $2,425,000 Halff Associates contract for design and construction of a Playa 7 pump station and a force main down Soncy Road to the gravity drains to West Amarillo Creek, from drainage bond proceeds. On August 25, 2026, on a consent agenda approved 4-0, Amendment No. 1 added $393,812 (total $2,818,812, CIP PRJ-560133). [1][2]
- Original
- $2,425,000
- Amendment
- $393,812
- Revised
- $2,818,812