· Context
City says 75% of identified Hollywood Road problems repaired; moving toward replacement
The City said 75% of the problems identified a year earlier had been repaired and that an additional $300,000 had been awarded on top of $17 million for repairs. Interim City Manager Floyd Hartman said the plant is in a flood plain and the City is moving toward completely replacing it. City officials said the City had not been fined for the overflow.[1]
What the sources say
- ✓ Verified
In June 2024 the City said 75% of the problems identified a year earlier had been repaired and that an additional $300,000 had been awarded on top of $17 million allocated for repairs after the floods.[1]
- Additional
- $300,000
- Prior allocation
- $17,000,000
- Share repaired
- 75%
- ✓ Verified
Floyd Hartman, Interim City Manager: Interim City Manager Floyd Hartman said: "Out in the floods last year there was some severe damage to the wastewater plant and out of that many overflows." He said the plant is in a flood plain and that the City is moving toward completely replacing it.[1]