Change Order No. 3 adds $189,701.70 for unmapped utility conflicts
On December 10, 2024 the council approved, 5-0 on the consent agenda, Change Order No. 3 for $189,701.70, bringing the S.J. Louis contract to $72,862,527.80 and adding 42 calendar days. It covered relocating a power pole and service meter, rerouting and replacing private gas service lines on two properties, and auger boring under two gas lines not shown in utility records, so an 18-inch line could carry flow from the Imhoff tank to the interceptor.[1][2]
Cole StanleyJosh CraftDon TippsTom ScherlenLes SimpsonMichael PriceS.J. Louis Construction of Texas, Ltd.
What the sources say
- ✓ Verified
Change Order No. 3 ($189,701.70) raised the contract to $72,862,527.80 and added 42 calendar days. The memo said the conflicts "were unknown by the City and its contractor at the time of bidding" and that staff was "seeking possible mechanisms for City reimbursement of some or all of these expenses." The council approved it on the December 10, 2024 consent agenda, 5-0. [1][2]
- Change order
- $189,702
- Revised contract
- $72,862,528