Change Order No. 2 adds $1,406,065.95 for longer tunnels and alignment changes
On June 11, 2024 the council approved, 5-0, Change Order No. 2 with S.J. Louis Construction of Texas for $1,406,065.95, raising the contract to $72,672,826.10. It extended tunneling at eight utility crossings, including 607 more feet of 72-inch tunnel at depths of 50 to 70 feet, and adjusted the alignment for site conditions the memo described as unknown.[1][2]
Cole StanleyJosh CraftDon TippsTom ScherlenLes SimpsonS.J. Louis Construction of Texas, Ltd.
What the sources say
- ✓ Verified
Change Order No. 2 ($1,406,065.95) raised the S.J. Louis contract from $71,266,760.15 to $72,672,826.10, adding 607 linear feet of 72-inch tunnel extensions at depths of 50 to 70 feet, modifying two manholes, replacing a water service line and adding 8 calendar days, to address "unknown conditions the contractor is encountering on-site." The council approved it 5-0 on June 11, 2024 (motion by Don Tipps, second by Josh Craft). [1][2]
- Change order
- $1,406,066
- Revised contract
- $72,672,826