Stolz Mechanical awarded $4.03 million Osage filter rehabilitation
On the consent agenda approved 5-0, the council awarded Bid No. 6851 to Stolz Mechanical Contractors for $4,029,950 to replace filter underdrains and media with stainless-steel underdrains. The memo said two underdrain systems had failed, reducing the plant's ability to produce water at full capacity, and that the lower-profile underdrains gave the City its best opportunity to ask TCEQ for an increase in the plant's overall flow rating. A May 2021 change order for sidewalks ($71,015) brought the contract to $4,090,665.[1][2][3]
Stolz Mechanical Contractors, LLC
What the sources say
- ✓ Verified
On August 11, 2020 the council approved, 5-0 on its consent agenda, Bid No. 6851 Osage Water Treatment Plant Filter Rehabilitation to Stolz Mechanical Contractors for $4,029,950, funded from project 523385 (WTP Filter Rehabilitation). [1][2]
- Amount
- $4,029,950
- ✓ Verified
City of Amarillo Director of Utilities (staff memo): The staff memo said two filter underdrain systems had failed, diminishing the ability to produce water at full capacity, and that standardizing on low-profile stainless-steel underdrains would give the City its best opportunity to ask TCEQ for an increase in the plant's overall flow rating. The documents reviewed do not show whether such a request was made or granted. [1]
- ✓ Verified
Change Order No. 2 to the Stolz filter rehabilitation contract added $71,015 for sidewalks for safe access; after Change Order No. 1 (a $10,300 reduction) the contract total became $4,090,665. It was on the May 11, 2021 consent agenda recorded in the draft minutes in the May 25, 2021 packet. [3]
- Original
- $4,029,950
- Change order 2
- $71,015
- Revised total
- $4,090,665