Canadian River Municipal Water Authority (CRMWA)
The Canadian River Municipal Water Authority (CRMWA) is a conservation and reclamation district the Texas Legislature created on May 27, 1953 to supply water to 11 member cities in the Panhandle and South Plains, including Amarillo. It operates Lake Meredith, the original aqueduct system that began deliveries in 1968, and the John C. Williams well field and aqueduct in Roberts County, which began delivering groundwater in 2001. A 17-member board appointed by the member cities governs it, and it bills the cities for its costs; its FY2024/25 budget was $36,996,301, of which $14,090,126 was allocated to Amarillo. In FY2024-25 it delivered 65,572 acre-feet, 51,863 of it groundwater.
Project profile: CRMWA II →
How to read this page
Every row says what kind of statement it is. Where sources give different figures, each is listed with its source under “Figures by source”; some disagree, some cover a different phase or date. Numbers link to the source list at the bottom.
- Fact
- Recorded in a document: a vote, a payment, a filing, a measurement.
- Commitment
- What a party has agreed to in a signed agreement or approved item.
- Plan
- What a party says it intends to build or do; it may change.
- Projection
- An estimate of a future effect by a named agency, consultant or plan.
- Estimate
- A cost or size figure given by a named party, with its date and basis where stated.
- Company statement
- What a company says about itself or its project, not independently checked.
What it is
- CreatedMay 27, 1953
- CRMWA was created on May 27, 1953 by Chapter 243, Acts of the 53rd Legislature (formerly article 8280-154 of Vernon's Texas Civil Statutes), as a conservation and reclamation district under Article 16, Section 59 of the Texas Constitution. The 2026 Panhandle Water Plan says it was created to distribute water from the Canadian River Project under the Canadian River Compact among Texas, New Mexico and Oklahoma. 1,2,3As of Dec 1, 2025
- Member cities11
- Amarillo, Borger, Brownfield, Lamesa, Levelland, Lubbock, O'Donnell, Pampa, Plainview, Slaton and Tahoka, with a combined population of 565,124 in 2025 (CRMWA). Amarillo, Borger and Pampa are in the Panhandle planning region; the other eight are in the Llano Estacado region. 1,3As of Dec 1, 2025
Schedule
- Board meetings
- The board meets quarterly (third Wednesday of January, second Wednesday of April, July and October). 2026 meetings were January 21, April 8, July 8 and October 14; minutes are available on request, not online. 6As of Oct 25, 2026
Money
- Budget, FY2024/25$36,996,301
- CRMWA's FY2024/25 original budget was $36,996,301: $12,015,911 operation and maintenance, $11,713,581 pumping energy and chemicals, and $13,266,809 bond payments. CRMWA bills member cities on a cost-reimbursement basis and trues up to actual costs after year end; the board adopts the budget in April. 1As of Dec 1, 2025
- Amarillo's share of budget$14,090,126 (FY2024/25)
- CRMWA's FY2024/25 budget allocated $14,090,126 to Amarillo ($4,103,834 O&M, $4,275,218 pumping energy and chemicals, $5,711,074 bond payments). Amarillo and Lubbock together make up 74.32% of CRMWA's annual revenue. The City's FY2026/27 budget book lists $14,216,749 for its CRMWA payment plus $4,021,325 of CRMWA bond debt service; the City's rate consultant put Amarillo's CRMWA cost at 24% of the water budget in FY2026. 1,7,8As of Sep 24, 2026
- City payments recorded$51,535,515.95
- The City's check registers record 72 payments totaling $51,535,515.95 to CRMWA between July 21, 2022 and May 14, 2026; the register does not say what each payment was for.9As of May 14, 2026
- FY2025 results
- Operating revenues were $17,507,037 in FY2025; net position rose $2,761,468 to $335,986,802. The audit (Bolinger, Segars, Gilbert & Moss) gave an unmodified opinion. 1As of Sep 30, 2025
- Debt outstanding$39,835,000 principal
- At September 30, 2025 CRMWA had $39,835,000 of bond principal outstanding ($45,463,067 with premium) in three series of subordinate lien contract revenue refunding bonds (2017, 2020 and 2023; the 2021 series was defeased in February 2025), the last maturing February 15, 2031. The bonds financed the groundwater project and water rights and are rated Aa3 by Moody's. Amarillo's share of principal owed by member cities was $13,930,261. 1,5As of Sep 30, 2025The ACFR's table labels this balance row "September 30, 2024"; it follows FY2025 principal payments of $9,350,000.
- Capital plan
- CRMWA adopted its first formal Capital Improvements Plan in 2025. Under the CRMWA II MOU it is to raise its CIP budget each year from October 1, 2026 for critical repairs (such as pipe under Lake Tanglewood, highways and railroads) and CRMWA II design. The size of the FY2026/27 increase was not found. 10,11PlanBy CRMWA (history page); CRMWA and member cities (MOU), Jun 23, 2026
Water
- Lake Meredith
- The Bureau of Reclamation built Sanford Dam and completed Lake Meredith in 1965, with conservation storage of 500,000 acre-feet under the Canadian River Compact; CRMWA's state permit allows diversion of up to 100,000 acre-feet a year for the member cities and 51,200 for industry. The lake was empty for 1,107 days from May 25, 2011 to June 12, 2014 in TWDB storage data, and was 44.6% full on October 15, 2026. On September 30, 2025 CRMWA reported 279,840 acre-feet in storage. 3,12,1As of Oct 15, 2026
- Original aqueduct
- Built 1963-1966 and in service since 1968, the aqueduct runs from Lake Meredith south through Amarillo and Lubbock to Lamesa, with branches to Borger and Pampa and to the southwestern and southern cities; it is mostly concrete pipe from 96 inches down to 8 inches and can deliver up to 118 million gallons a day. Four pumping plants lift water about 800 feet to Amarillo. Lengths are given as 322 miles (aqueduct page), 326 miles (MOU) and about 400 miles of pipe including the groundwater system (MOU appendix). 13,11As of Oct 25, 2026
- Roberts County well field
- CRMWA began buying Roberts County water rights in 1996, broke ground on the groundwater project in 2000 and placed the John C. Williams Aqueduct and Wellfield in service in December 2001. It added wells in 2008 and 2010-2011 (44 wells, 88 MGD); capacity had fallen to 75.8 MGD by FY2025, and four new wells (about 7 MGD) were due in summer 2026. The 54-inch groundwater aqueduct carries up to 65 MGD (69,000 acre-feet a year). 1As of Dec 1, 2025
- Groundwater rightsjust over 456,000 acres
- CRMWA holds water rights on just over 456,000 acres in Roberts and adjacent counties (456,993 in the 2026 plan), including 211,000 acres bought in late 2011; the plan calls it the largest holder of groundwater rights in Texas. 1,3As of Dec 1, 2025
- Deliveries, FY2024-2565,572 acre-feet
- In the fiscal year ended September 30, 2025 CRMWA delivered 65,572 acre-feet to member cities and their customers: 13,708 from Lake Meredith and 51,863 from the well field. Amarillo received 27,119 acre-feet. 1As of Sep 30, 202527,119 is 41.4% of 65,572 (our calculation).
- Amarillo's allocation
- Sources give different figures for Amarillo's share.
- Figures by source
- 32,240 acre-feet (37.1%) · FY2025-26 allocation and proposed FY2026-27 allocation, of 87,000 acre-feet1
- 41.6% · Five-year average share of deliveries (same table)1
- about 55% · CRMWA general manager to the council, June 23, 2026 (as reported): share of CRMWA supply Amarillo uses14
- Supply vs. need
- The 2026 plan puts CRMWA's current supply at 77,000 acre-feet a year in 2030 against demands of 97,421, and 54,333 in 2080 against 118,345. CRMWA's annual report says member cities need 37 billion gallons a year while it can supply 22.5 billion (69,000 acre-feet), and that water quality limits lake water to about 25% of deliveries. 3,1ProjectionBy Panhandle Water Planning Group (2026 plan); CRMWA (FY2025 annual report), Dec 1, 2025
Board and management
- Board17 directors
- Each member city's governing body elects two directors if it has 10,000 or more people and one if fewer, for two-year terms; directors must be qualified voters and property-owning taxpayers of the city and may not be members of its governing body or employees. The board lists 17 directors: two each from Amarillo, Borger, Levelland, Lubbock, Pampa and Plainview, and one each from Brownfield, Lamesa, O'Donnell, Slaton and Tahoka. The board hires the general manager. 1,15As of Oct 25, 2026
Related parties
City of Amarillo
Member city; two directors; largest allocation (37.1% for FY2025-26)15,1
City of Lubbock
Member city; two directors; allocation equal to Amarillo's for FY2025-26 (32,240 acre-feet)15,1
U.S. Bureau of Reclamation
Built Sanford Dam and the Canadian River Project; grant partner on salinity and desalination studies3,1
Panhandle Groundwater Conservation District
Permits CRMWA's Roberts County wells (up to 69,000 acre-feet a year under the original permit)16,17
Storylines
- CRMWA II: the Canadian River Municipal Water Authority's proposed second groundwater pipeline (2012-2038)23 events naming Canadian River Municipal Water Authority
Events
- CRMWA's John C. Williams Wellfield and Aqueduct begin delivering Roberts County groundwater
- CRMWA expands its Roberts County well field to fill the 65 MGD groundwater aqueduct
- CRMWA begins discussing the CRMWA II concept with its board and member cities
- CRMWA uses unspent bond funds for a CRMWA II route study and easements
- Lake Meredith begins to recover and the immediate need for CRMWA II subsides
- CRMWA's original main pipeline has two leaks within 30 days; a 2016 survey finds segments to reinforce
- Archeological survey of the proposed CRMWA II pipeline route in four Panhandle counties
- 2016 regional water plans list "Expand Capacity CRMWA II" as a recommended strategy
- Panhandle planning group ranks CRMWA II pipeline projects for the 2021 regional water plan
- City check register: $51.5 million paid to CRMWA, July 2022 to May 2026
- CRMWA staff begin meeting each member city about CRMWA II timing
- CRMWA adopts its first formal Capital Improvements Plan
- CRMWA board meetings in July and October 2025 discuss CRMWA II timing with member cities
- CRMWA general manager briefs the Amarillo City Council on water supply and the planned 70-mile pipeline
- Panhandle planning group adopts the 2026 regional water plan with CRMWA II at about $800 million
- CRMWA board hosts a member-city roundtable on CRMWA II
- CRMWA board agenda takes up its Capital Improvements Plan, FY2026/27 budget and a CRMWA II update
- Rate consultant projects Amarillo's CRMWA cost rising to about $39.5 million by FY2036 as CRMWA II is phased in
- Amarillo City Council approves the non-binding CRMWA II memorandum of understanding, 4-0
- FY2026/27 budget book raises the City's CRMWA payment line to $14.2 million
- CRMWA board regular meeting scheduled in Plainview
- Expected: CRMWA issues debt to build CRMWA II (MOU target 2034)
- Expected: CRMWA II operational by the end of 2038 (MOU target)
City payments
From the City's check register. The register records payees, not projects, so these totals are every payment to the name, whatever it was for.
- CANADIAN RIVER MUNC WATER AUTH$53.7M · 74 payments, Jul 21, 2022 – Jul 9, 2026
Not public, or not found
- CRMWA FY2025/26 and FY2026/27 adopted budgets. Checked: CRMWA Financial Reports page (only the FY2025 ACFR with the FY24/25 budget), April 8, 2026 agenda (budget approval listed, outcome not posted)
- Board minutes for 2026 meetings. Checked: CRMWA agendas page ("available upon request")
- Directors' appointment dates and terms. Checked: CRMWA board page, ACFR, City boards portal (not re-fetched)