CRMWA II: the Canadian River Municipal Water Authority's proposed second groundwater pipeline (2012-2038)

CRMWA II is a proposed second pipeline of about 70 miles (67 miles in the 2026 Panhandle Water Plan) to carry groundwater from the Canadian River Municipal Water Authority's Roberts County well field to its 11 member cities, including Amarillo. CRMWA says it began discussing the concept in 2012, when drought left Lake Meredith supplying no water, and used unspent bond funds in 2013 for a route study and easements. The project has appeared in the regional water plans since the 2016 cycle. On June 23, 2026 the Amarillo City Council voted 4-0 to approve a non-binding memorandum of understanding among CRMWA and the member cities. The MOU sets an expectation that CRMWA II is operational by the end of 2038, with CRMWA issuing construction debt in 2034 (each member city council must approve CRMWA debt) and raising its capital budget from October 1, 2026 to pay for critical repairs and design. CRMWA's general manager put the cost at about $1.2 billion, with about $450 million as Amarillo's portion; the 2026 Panhandle Water Plan estimated about $800 million at September 2023 prices. The City's rate consultant projected Amarillo's CRMWA cost rising from about $14.25 million in FY2026 to about $39.52 million in FY2036.

A storyline groups dated events in order. It is a chronology, not an argument; it does not say why anything happened. All storylines

Where the story starts depends on the framing

  1. · Context

    CRMWA's John C. Williams Wellfield and Aqueduct begin delivering Roberts County groundwater

    Until 2001 all water CRMWA delivered to its member cities came from Lake Meredith. The John C. Williams Wellfield and Aqueduct, which carries groundwater from Roberts County, was placed in operation in December 2001, introducing groundwater into the original system at Borger (for Borger and Pampa) and between Sanford Dam and Amarillo (for the other member cities).[1][2]

    Canadian River Municipal Water Authority (CRMWA)

    • ✓ Verified

      CRMWA states that before 2001 all of the water it delivered to member cities came from Lake Meredith, and that the John C. Williams Wellfield and Aqueduct began delivering groundwater in 2001. Its history page says the well field was placed in operation in December 2001, providing about 35% of the total water demand of the member cities.[2][1]

      Share of member city demand
      35%
  2. · Precursor

    CRMWA expands its Roberts County well field to fill the 65 MGD groundwater aqueduct

    During the drought that began in 2001, CRMWA doubled the well production capacity of the John C. Williams Wellfield so that the groundwater aqueduct ran at its full capacity of 65 million gallons per day. CRMWA describes that aqueduct capacity as the limit on how much groundwater it can deliver. Sources give 2010 or 2011 for the expansion.[2][1][3]

    Canadian River Municipal Water Authority (CRMWA)

    • ⚠ Sources differ

      Sources differ on the year CRMWA expanded the John C. Williams Wellfield to fill its groundwater aqueduct.

      Reported value 1[2][1]

      Year
      2,010

      CRMWA's MOU recital ("In 2010 ... CRMWA doubled the well production capacity") and history page (2010: 15 high-capacity wells added, 45 wells in total)

      Reported value 2[3]

      Year
      2,011

      General Manager Drew Satterwhite, as reported by the Amarillo Tribune: in 2011 CRMWA expanded the well field and doubled its capacity

    • ✓ Verified

      CRMWA states that the 65 million gallons per day capacity of its groundwater aqueduct is the limiting factor in how much groundwater it can deliver to member cities. In September 2025 the general manager described the system as 47 wells and 48 miles of 54-inch pipe able to bring 65 MGD of groundwater to the member cities.[2][3]

      Aqueduct capacity mgd
      65
      Wells
      47
  3. · Origin

    CRMWA begins discussing the CRMWA II concept with its board and member cities

    In 2012 and 2013 drought left Lake Meredith supplying none of CRMWA's deliveries; all water delivered came from groundwater. CRMWA states that in 2012 it began discussing the concept of CRMWA II, a second pipeline to carry Roberts County groundwater, with its Board of Directors and member cities.[2][1]

    Canadian River Municipal Water Authority (CRMWA)

    • ✓ Verified

      The MOU's background section states: "In 2012, CRMWA began discussing the concept of CRMWA II with the Board of Directors and Member Cities." It describes CRMWA II as a proposed second pipeline to transport groundwater from Roberts County to the member cities.[2]

    • ✓ Verified

      CRMWA states that in 2012 and 2013 all of the water it delivered came from groundwater because drought affected the quantity and quality of Lake Meredith water; its history page says 2012 was the first year since deliveries began in 1968 that no water was produced from the lake.[2][1]

  4. · Related development

    CRMWA uses unspent bond funds for a CRMWA II route study and easements

    CRMWA states that in 2013 it used unspent bond funds to hire an engineering firm for a route study and then to acquire easements for building CRMWA II. The sources reviewed do not name the firm, the bond issue or the amount spent.[2]

    Canadian River Municipal Water Authority (CRMWA)

    • ✓ Verified

      CRMWA states that in 2013 it used unspent bond funds to hire an engineering firm to perform a route study and then to acquire easements for the construction of CRMWA II. The sources reviewed do not name the firm, the bond series or the amounts.[2]

  5. · Context

    Lake Meredith begins to recover and the immediate need for CRMWA II subsides

    CRMWA states that Lake Meredith began to recover in 2014, with water levels generally rising through 2020, and that with rising levels and improving water quality the immediate need to bring CRMWA II online subsided.[2][1]

    Canadian River Municipal Water Authority (CRMWA)

    • ✓ Verified

      CRMWA states that in 2014 Lake Meredith began to recover, with water levels generally rising through 2020, and that "with the rising water levels and improving water quality, the immediate need to bring CRMWA II online subsided."[2]

  6. · Context

    CRMWA's original main pipeline has two leaks within 30 days; a 2016 survey finds segments to reinforce

    CRMWA reports that in 2015, after almost 50 years of service, its main pipeline (72-inch to 96-inch) had two leaks within 30 days, and that a 2016 internal electromagnetic survey of 55 miles of pipe identified segments to reinforce or replace. CRMWA later cited deterioration of the original pressure section between Lake Meredith and Amarillo as one reason CRMWA II remains needed.[1][2]

    Canadian River Municipal Water Authority (CRMWA)

    • ✓ Verified

      CRMWA's history page states that in 2015 its main pipeline (72-inch to 96-inch internal diameter) had two leaks within 30 days, and that a 2016 internal electromagnetic survey of 55 miles of pipe found segments needing reinforcement or replacement; CRMWA then bypassed three areas and placed external clamps on another 69 joints.[1]

      Leaks 2015
      2
      Miles surveyed 2016
      55
      Joints clamped
      69
    • ✓ Verified

      The MOU states CRMWA II would provide redundancy for 25 miles of 1968 pipeline that delivers 100% of CRMWA water to all member cities except Borger and Pampa, 48 miles of 2001 pipeline that delivers all of CRMWA's groundwater, and 23 miles of 1968 pipeline serving Pampa. It cites signs of deterioration in the original pressure section of the aqueduct between Lake Meredith and Amarillo as one reason CRMWA II remains needed.[2]

  7. · Related development

    2016 regional water plans list "Expand Capacity CRMWA II" as a recommended strategy

    The TWDB summaries of the 2016 Panhandle (A) and Llano Estacado (O) regional water plans list "Expand Capacity CRMWA II" among each region's ten recommended strategies with the largest supply volume, at 24,000 acre-feet per year in 2070. Regional plans become the basis of the State Water Plan.[4][5]

    Canadian River Municipal Water Authority (CRMWA)

    • ✓ Verified

      The TWDB summary of the 2016 Panhandle (A) Regional Water Plan lists "Expand Capacity CRMWA II" at 24,000 acre-feet per year in 2070, serving a population of 388,000 across 3 water user groups. The 2016 Llano Estacado (O) summary lists the same strategy at 24,000 acre-feet per year, serving 478,000 across 8 water user groups.[4][5]

      Supply acre feet per year 2070
      24,000
    • ✓ Verified

      The 2016 Panhandle (A) summary's largest capital-cost projects include "Expansion of Roberts County Well Field (Ogallala Aquifer) in 2024 - CRMWA2" at $250,299,000 (online decade 2030), sponsored by CRMWA. The summary does not state whether that project is the CRMWA II pipeline.[4]

      Capital cost
      $250,299,000
  8. · Related development

    Panhandle planning group ranks CRMWA II pipeline projects for the 2021 regional water plan

    The Panhandle (A) planning group's prioritization of recommended projects for the 2021 regional water plan, which the TWDB uses as one criterion in ranking projects that seek SWIFT funding, listed a "CRMWA II Shared Pipeline" ($301,355,000), a "CRMWA II CRMWA Pipeline" ($100,489,000) and an Amarillo project, "Amarillo Well Field to CRMWA II Transmission Pipeline" ($92,956,000).[6][7]

    Canadian River Municipal Water Authority (CRMWA)

    • ✓ Verified

      In the Region A prioritization for the 2021 regional water plans (as of November 5, 2020), CRMWA's "CRMWA II Shared Pipeline" ranked 11th with a capital cost of $301,355,000 and "CRMWA II CRMWA Pipeline" ranked 16th at $100,489,000; Amarillo's "Amarillo Well Field to CRMWA II Transmission Pipeline" ranked 64th at $92,956,000. The TWDB states a project's regional prioritization is one of the criteria it uses to rank projects seeking SWIFT funding.[6]

      Shared pipeline
      $301,355,000
      Crmwa pipeline
      $100,489,000
      Amarillo transmission
      $92,956,000
    • ✓ Verified

      The TWDB summary of the 2021 Panhandle (A) plan lists both CRMWA II pipeline projects with an online decade of 2030 and the Amarillo transmission pipeline with an online decade of 2070.[7]

    • ✓ Verified

      The sources reviewed for this record do not show that CRMWA has applied for or received State Water Implementation Fund for Texas (SWIFT) or other TWDB financing for CRMWA II. The MOU states that funding design early would increase CRMWA's ability to access state and federal funding with a shovel-ready project and that CRMWA will keep CRMWA II in the State Water Plan to maximize state funding options.[2][6]

  9. · Context

    City check register: $51.5 million paid to CRMWA, July 2022 to May 2026

    The City's published check registers record 72 payments totaling $51,535,515.95 to the Canadian River Municipal Water Authority between July 21, 2022 and May 14, 2026, under two payee names. The register does not tie payments to projects or separate water purchases from debt service.[8]

    Canadian River Municipal Water Authority (CRMWA)

    • ✓ Verified

      The City's check register records 72 payments totaling $51,535,515.95 to the Canadian River Municipal Water Authority between 2022-07-21 and 2026-05-14: by fiscal year, $3,760,076.43 (FY2022, July-September only), $14,593,579.98 (FY2023), $13,932,560.59 (FY2024), $12,200,792.79 (FY2025) and $7,048,506.16 (FY2026, October 2025-May 2026 only). The register does not identify what each payment was for (water purchases, operations or debt service) and does not tie any payment to CRMWA II.[8]

      Total
      $51,535,516
      Payments
      72
      Fy2022
      $3,760,076
      Fy2023
      $14,593,580
      Fy2024
      $13,932,561
      Fy2025
      $12,200,793
      Fy2026 partial
      $7,048,506

      See the payments in the check register →

    • ✓ Verified

      The register uses two payee names. "CANADIAN RIVER MUNC WATER AUTH" appears on 65 payments totaling $45,291,884.15 (July 2022-July 2024 by check, and January 2025-May 2026 by EFT); "CANADIAN RIVER MUNICIPAL WATER" appears on 7 checks totaling $6,243,631.80 between 2024-08-12 and 2024-12-09. The change back in January 2025 coincides with the register's switch from check numbers to EFT references; the two names are the same authority.[8]

      Munc water auth
      $45,291,884
      Munc water auth payments
      65
      Municipal water
      $6,243,632
      Municipal water payments
      7

      See the payments in the check register →

  10. · Related development

    CRMWA staff begin meeting each member city about CRMWA II timing

    CRMWA states that since 2023 its staff has met with each member city at least twice to discuss CRMWA II timing and what it would provide: more water, supply redundancy and partial infrastructure redundancy.[2]

    Canadian River Municipal Water Authority (CRMWA)

    • ✓ Verified

      CRMWA states its staff has met with each member city at least twice since 2023 to discuss CRMWA II timing and what it will provide, such as increased water availability, water supply redundancy and partial infrastructure redundancy.[2]

  11. · Context

    CRMWA adopts its first formal Capital Improvements Plan

    CRMWA states that in 2025 it adopted its first formal Capital Improvements Plan, with prioritized projects and a funding plan, to address aging infrastructure.[1]

    Canadian River Municipal Water Authority (CRMWA)

    • ✓ Verified

      CRMWA's history page states that in 2025 it adopted its first formal Capital Improvements Plan to address aging infrastructure, including prioritized projects and a funding plan, and that an engineering study reported the firm yield of Lake Meredith as 16,700 acre-feet per year, compared with an original estimate of 126,000 and an estimate of 76,000 in the 1980s.[1]

      Lake meredith firm yield acre feet
      16,700
  12. · Related development

    CRMWA board meetings in July and October 2025 discuss CRMWA II timing with member cities

    At CRMWA's July and October 2025 board meetings, the board, staff and member cities in attendance discussed CRMWA II in detail. CRMWA states the preferred timelines of the member cities varied widely, that the consensus was the project is critical, and that the meetings showed the need for a roundtable to set a timeline.[2]

    Canadian River Municipal Water Authority (CRMWA)

    • ✓ Verified

      CRMWA states that at its July and October 2025 board meetings "the perfect timeline for the Member Cities varied widely," that the consensus was the project is critical to the member cities' futures, and that the meetings reinforced the need for a roundtable so a timeline could be set.[2]

  13. · Related development

    CRMWA general manager briefs the Amarillo City Council on water supply and the planned 70-mile pipeline

    CRMWA General Manager Drew Satterwhite gave the council an update on CRMWA's history, Lake Meredith, the Roberts County well field and the planned additional 70-mile pipeline, which he said would bypass the original aqueduct and provide redundancy for Amarillo. Asked by Councilmember Don Tipps about Fermi America's campus, he said CRMWA's models were not forecasting that Fermi's demand would come from CRMWA.[9][3]

    Drew SatterwhiteDon TippsDonny HooperCole StanleyCanadian River Municipal Water Authority (CRMWA)Fermi America (Fermi, Inc.)

    • ✓ Verified

      Drew Satterwhite: The September 9, 2025 council minutes record a "Canadian River Municipal Water Authority update" presented by Drew Satterwhite. As reported by the Amarillo Tribune, Satterwhite said the planned 70-mile pipeline would let CRMWA fill its original 1960s aqueduct with groundwater, bypass the original aqueduct and provide redundancy for Amarillo, and that 100% of the water CRMWA delivers to Amarillo currently passes through a pipe approaching 60 years old.[9][3]

    • ✓ Verified

      Member cities with more than 10,000 people appoint two CRMWA directors and smaller cities appoint one. Amarillo's appointed CRMWA directors are Johnny Mize and Roy Urrutia.[3][10]

    • ✓ Verified

      Drew Satterwhite: Asked by Councilmember Don Tipps about the possible effect of Fermi America's campus on CRMWA's supply, Satterwhite said CRMWA's models were not forecasting that Fermi's demand would come from CRMWA, and that it did not concern him with regard to CRMWA's Roberts County groundwater.[3]

    • ✓ Verified

      None of the sources reviewed for this record states that CRMWA II is planned or sized to serve Fermi America's Project Matador. CRMWA and the City attribute the need for CRMWA II to Lake Meredith's declining reliability and water quality, aging infrastructure and growing member-city demand. Coverage of the April 2026 rate study lists Fermi's water supply and CRMWA costs as separate factors.[3][2][11]

  14. · Related development

    Panhandle planning group adopts the 2026 regional water plan with CRMWA II at about $800 million

    The Panhandle Water Planning Group adopted the 2026 Panhandle Water Plan, which describes CRMWA II as a new 67-mile pipeline from Roberts County, costed for a 72-inch pipe, and estimates the cost of the well field expansion including the CRMWA II pipeline at about $800 million (September 2023 prices). The plan states that Amarillo considered moving its own Roberts/Ochiltree water through CRMWA II but decided to develop that water independently. The TWDB approved the 2026 regional water plans on January 22, 2026.[12][13][14]

    Canadian River Municipal Water Authority (CRMWA)

    • ✓ Verified

      The 2026 Panhandle Water Plan states that CRMWA plans a second pipeline (CRMWA II) providing at least 65,000 acre-feet per year, raising total capacity from the Roberts County well field to at least 130 MGD; it assumes a new 67-mile pipeline from Roberts County to CRMWA's existing system with tie-ins to Amarillo's and Pampa's systems, costed for a 72-inch pipe with final sizing to be set in design. It says the exact timing "is currently being discussed with CRMWA's member cities but is expected to occur within the next decade."[12]

      New supply acre feet per year
      65,000
      Total capacity mgd
      130
      Pipeline miles
      67
    • ✓ Verified

      Estimate: the 2026 Panhandle Water Plan puts the cost to expand the Roberts County well field at "around $800 million," covering the CRMWA II pipeline, new wells for 80,000 acre-feet per year and well field piping, at September 2023 price levels. The TWDB's data summary of the plan lists the project "Expansion of Roberts County Well Field (Ogallala Aquifer) - CRMWA2" at $767,771,000, online decade 2030.[12][14]

      Plan estimate
      $800,000,000
      Twdb summary capital cost
      $767,771,000
    • ✓ Verified

      The 2026 plan states that Amarillo "considered partnering with CRMWA to move its Roberts/Ochiltree water through the CRMWA II pipeline but ultimately decided to pursue developing the water independently," and that "the former joint CRMWA and Amarillo CRMWA II pipeline will now be developed individually." It puts Amarillo's current delivery capacity from CRMWA at 42,987 acre-feet per year, which CRMWA intends to increase with CRMWA II.[12]

      Amarillo crmwa delivery capacity acre feet
      42,987
    • ✓ Verified

      The Panhandle Water Planning Group adopted the 2026 plan on September 24, 2025, and the TWDB Board approved the adopted 2026 regional water plans on January 22, 2026. The TWDB's Region A data summary lists "Expand Capacity CRMWA 2" at 10,720 acre-feet per year in 2080; its Region O summary lists the same strategy at 18,699 acre-feet per year.[12][13][14]

  15. · Starting point

    CRMWA board hosts a member-city roundtable on CRMWA II

    CRMWA's January 21, 2026 board meeting in Plainview listed a CRMWA II right-of-way update and a roundtable on CRMWA II. CRMWA states that each member city discussed its water needs and timing, that critical repairs (such as reinforcing pipe under Lake Tanglewood, highways and railroad crossings) were to be funded before a CRMWA II debt issuance, and that the parties reached consensus on a path forward. CRMWA's history page states its board voted unanimously in 2026 to move forward with a new wellfield and pipeline to be online in 2038.[15][2][1]

    Canadian River Municipal Water Authority (CRMWA)

    • ✓ Verified

      The agenda for CRMWA's January 21, 2026 board meeting in Plainview lists item 13, "CRMWA II Right of Way Update," and item 20, "Round Table Meeting to Discuss CRMWA II," for consideration and possible action.[15]

    • ✓ Verified

      CRMWA states that at the January 2026 roundtable each member city discussed its water supply needs and timing and when CRMWA II should come online; that the parties discussed critical projects such as reinforcing existing pipe under Lake Tanglewood, highways and railroad crossings, to be done and funded before a CRMWA II debt issuance; and that the parties reached consensus on a path forward.[2]

    • ✓ Verified

      CRMWA's history page states that in 2026 "the Board of Directors unanimously voted to move forward with a plan to build a new wellfield and pipeline that would be online in the year 2038." The page does not give the meeting date, and no CRMWA minutes were found online.[1]

  16. · Related development

    CRMWA board agenda takes up its Capital Improvements Plan, FY2026/27 budget and a CRMWA II update

    CRMWA's April 8, 2026 board agenda listed discussion and possible action on the Authority's Capital Improvements Plan, approval of the FY2026/27 budget, and a CRMWA II update. The MOU later provides that CRMWA will discuss CRMWA II and the CIP at each April board meeting. The outcomes of the April 8 items were not found.[16]

    Canadian River Municipal Water Authority (CRMWA)

    • ✓ Verified

      The agenda for CRMWA's April 8, 2026 board meeting lists item 5, "Discussion and possible action related to the Authority's Capital Improvement's Plan"; item 6, "Approve budget for FY 2026/2027"; and item 12, "CRMWA II Update." The actions taken were not found.[16]

  17. · Related development

    Rate consultant projects Amarillo's CRMWA cost rising to about $39.5 million by FY2036 as CRMWA II is phased in

    Presenting the water and wastewater rate study, Chris Ekrut of NewGen Strategies and Solutions told the council that Amarillo's annual CRMWA cost of about $14.25 million in FY2026 was projected to reach about $39.52 million in FY2036, and that CRMWA capital costs were expected to ramp up from 2027 to phase in future CRMWA II costs, with CRMWA II debt anticipated in 2034.[11][17][18]

    Grayson PathCole StanleyNewGen Strategies and SolutionsCanadian River Municipal Water Authority (CRMWA)

    • ✓ Verified

      Projection (rate study, as reported): the City purchases wholesale water from CRMWA and pays an allocated share of CRMWA's annual debt service; its annual CRMWA cost of $14.25 million in FY2026 is projected to rise to about $39.52 million in FY2036, going from 24% to 40% of the water budget. NewGen expected budgeted CRMWA capital costs to ramp up beginning in 2027 to phase in future CRMWA II costs, with additional debt anticipated for CRMWA II in 2034.[11][18]

      Crmwa cost fy2026
      $14,250,000
      Crmwa cost fy2036
      $39,520,000
      Share of water budget fy2026
      24%
      Share of water budget fy2036
      40%
    • ✓ Verified

      Chris Ekrut (NewGen Strategies and Solutions): Ekrut said the future water supply from CRMWA was then anticipated around 2033-34, "but we will be seeing costs increases as soon as 2027, so we have to factor that in."[11]

    • ✓ Verified

      The April 14, 2026 minutes record item 6.1, "Presentation of Water & Wastewater Rate Study," with City Manager Grayson Path introducing Chris Ekrut of NewGen Strategies and Solutions, LLC. The agenda packet for that meeting does not include the presentation slides.[17]

  18. · Peak

    Amarillo City Council approves the non-binding CRMWA II memorandum of understanding, 4-0

    The council voted 4-0 (Councilmember Don Tipps absent) to approve a non-binding MOU among CRMWA and its 11 member cities on CRMWA II. The MOU states the parties' expectation that CRMWA II be operational by the end of 2038, which would require CRMWA to issue construction debt in 2034, and that CRMWA raise its Capital Improvements Plan budget each year from October 1, 2026 for critical repairs and CRMWA II design. The City's agenda summary said Amarillo's annual contribution to CRMWA will increase. CRMWA's general manager estimated the project at $1.2 billion, about $450 million of it Amarillo's portion.[19][2][20][21]

    Cole StanleyTim ReidDavid PrescottLes SimpsonDon TippsGrayson PathDrew SatterwhiteCanadian River Municipal Water Authority (CRMWA)

    • ✓ Verified

      Item 6.5: on a motion by Councilmember David Prescott, seconded by Councilmember Les Simpson, the council approved the Memorandum of Understanding between the City of Amarillo and CRMWA 4-0 (ayes: Cole Stanley, Tim Reid, David Prescott, Les Simpson; absent: Don Tipps). The item asked the council to authorize the Mayor to execute the non-binding MOU, as ten other member cities were also asked to do.[19][2]

      Ayes
      4
      Noes
      0
    • ✓ Verified

      The City's agenda summary says the need for CRMWA II is driven by the long-term decline in Lake Meredith's reliability and water quality, aging infrastructure and growing demand; that CRMWA II would raise CRMWA's groundwater delivery capacity from 65 MGD to 112 MGD; and that the MOU reflects consensus reached at a January 2026 member-city roundtable.[2]

      Capacity before mgd
      65
      Capacity after mgd
      112
    • ✓ Verified

      The agenda item's funding summary states: "The City of Amarillo annual contribution will increase to help prepare our budget over time for the eventual large CRMWA II construction costs. Our increase payments between now and construction will go towards our share of any CIPs that CRMWA builds that the City of Amarillo benefits directly from, as well as designing the CRMWA II project to make it ready for construction." It gives no dollar amount.[2][21]

    • ✓ Verified

      The MOU, made under the Interlocal Cooperation Act among CRMWA and the cities of Amarillo, Borger, Brownfield, Lamesa, Levelland, Lubbock, O'Donnell, Pampa, Plainview, Slaton and Tahoka, states the parties agree CRMWA II should be operational by the end of 2038; that construction would take about four years, requiring CRMWA to issue construction debt in 2034; that CRMWA should increase its Capital Improvements Plan budget each year starting October 1, 2026 and use it for critical infrastructure improvements and CRMWA II design, prioritizing the critical improvements; and that CRMWA will discuss CRMWA II and the CIP at each April board meeting at a minimum. The MOU is non-binding, takes effect on the date of the last signature and lasts until CRMWA II is operational.[2]

    • ✓ Verified

      The MOU states that each member city has rights to a defined allocation of CRMWA's water supply and system capacity, and that "each Member City's city council is required to approve CRMWA's debt issuances."[2]

    • ✓ Verified

      Drew Satterwhite: Estimate: presenting to the council, CRMWA General Manager Drew Satterwhite put the cost of CRMWA II at about $1.2 billion, of which about $450 million would be the City of Amarillo's portion, and estimated that Amarillo uses about 55% of CRMWA's supply. He said the project would include 70 miles of 72-inch pipeline, additional wells and two pump stations, and would take about eight years to complete if all member cities approve.[20]

      Total cost
      $1,200,000,000
      Amarillo portion
      $450,000,000
      Amarillo share of supply
      55%
    • ✓ Verified

      Cole Stanley: Mayor Cole Stanley said the existing line is "a six-foot pipe that's concrete that's underground under high-pressure conditions and it's over 50 years old and it is a single point of failure," and that "having an alternate line and opening up the additional well field and capacity is what the future of Amarillo needs."[21]

    • ⚠ Sources differ

      Cost estimates for CRMWA II differ by source, date, price basis and scope.

      Reported value 1[20]

      Amount
      $1,200,000,000

      Total project, CRMWA general manager's estimate presented June 23, 2026 (Amarillo portion about $450 million)

      Reported value 2[12]

      Amount
      $800,000,000

      "Around $800 million" for the CRMWA II pipeline, new wells and well field piping, 2026 Panhandle Water Plan, September 2023 price levels

      Reported value 3[14]

      Amount
      $767,771,000

      Capital cost of "Expansion of Roberts County Well Field (Ogallala Aquifer) - CRMWA2" in the TWDB's Region A data summary of the 2026 plan

      Reported value 4[6]

      Amount
      $401,844,000

      Sum of the two 2021-plan CRMWA II pipeline projects ($301,355,000 shared pipeline + $100,489,000 CRMWA pipeline), excluding Amarillo's separate $92,956,000 transmission pipeline

    • ⚠ Sources differ

      Sources describe the CRMWA II pipeline length and number of pump stations differently.

      Reported value 1[2]

      Pipeline miles
      70
      Pump stations
      2-3

      MOU: approximately 70 miles of large-diameter pipeline with 2-3 pump stations

      Reported value 2[20]

      Pipeline miles
      70
      Pump stations
      2

      CRMWA general manager to the council, June 23, 2026: 70 miles of 72-inch pipeline and two pump stations

      Reported value 3[12]

      Pipeline miles
      67

      2026 Panhandle Water Plan: assumed new 67-mile pipeline, costed for 72-inch pipe

  19. · Related development

    FY2026/27 budget book raises the City's CRMWA payment line to $14.2 million

    The FY2026/27 budget book (after council review) budgets $14,216,749 for the "Pmnt to CRMWA - M" line in the Surface Water Treatment cost center, up $4,965,794 from the FY2025/26 budget of $9,250,955, plus $4,021,325 of debt service on CRMWA refunding bonds. The book does not state the reason for the increase. At the September 29, 2026 meeting where the budget was adopted with an 11% water and sewer fee increase, Councilmember David Prescott cited a new CRMWA pipeline among large upcoming water expenses.[22][23]

    David PrescottCole StanleyCanadian River Municipal Water Authority (CRMWA)

    • ✓ Verified

      In the FY2026/27 budget book (after council review, September 24, 2026), the Surface Water Treatment cost center's line "SC78000 - Pmnt to CRMWA - M" shows actual spending of $7,216,296 (FY2022/23), $7,640,941 (FY2023/24) and $6,489,367 (FY2024/25), a FY2025/26 budget of $9,250,955 (revised estimate $9,000,000) and a FY2026/27 budget of $14,216,749, an increase of $4,965,794 over the FY2025/26 budget. The book does not state the reason for the increase.[22]

      Fy2023 actual
      $7,216,296
      Fy2024 actual
      $7,640,941
      Fy2025 actual
      $6,489,367
      Fy2026 budget
      $9,250,955
      Fy2026 revised
      $9,000,000
      Fy2027 budget
      $14,216,749
      Increase
      $4,965,794
    • ✓ Verified

      The same budget book lists $4,021,325 in FY2026/27 debt service (principal $3,513,882, interest $507,443) on the City's share of CRMWA refunding bonds (2017, 2020 and 2023 series), paid from the water and sewer system, with $12,677,194 outstanding; the schedule shows these bonds retired by FY2031.[22]

      Fy2027 debt service
      $4,021,325
      Outstanding
      $12,677,194
    • ✓ Verified

      David Prescott: At the September 29, 2026 meeting, after Mayor Cole Stanley asked that the council consider a rate decrease if the pending rate study finds the 11% fee increase is not needed, Councilmember David Prescott said he was concerned about large upcoming water expenses, such as a new CRMWA pipeline.[23]

    • ✓ Verified

      The City described the FY2026/27 11% water and sewer fee increase as 8% for capital improvements and 3% for debt service on the Hollywood Road wastewater loan. None of the sources reviewed for this record states that any part of that increase is for CRMWA II, and none shows a separate CRMWA II charge to Amarillo utility customers.[23][2][11]

  20. Scheduled

    CRMWA board regular meeting scheduled in Plainview

    CRMWA's board agendas page lists a regular board meeting on October 14, 2026 at 10:00 a.m. in Plainview. No agenda was posted when the page was retrieved on October 11, 2026.[24][25]

    Canadian River Municipal Water Authority (CRMWA)

    • ✓ Verified

      CRMWA's board agendas page lists a regular meeting on October 14, 2026 at 10:00 a.m. at the Plainview Country Club; no agenda was linked when retrieved on October 11, 2026; an agenda was linked by October 14, 2026.[24][25]

    • ✓ Verified

      The posted agenda for CRMWA's October 14, 2026 regular board meeting (10:00 a.m., Plainview Country Club/Convention Center) includes item 15, "Discussion and possible action on all matters incident and related to CRMWA II and the purchase of easements"; item 19, on "energy and industrial developments projects over CRMWA's groundwater rights"; item 10.c, possible action setting 2027 water allocations; item 17, potential litigation regarding easement rights on the Slaton Lateral pipeline; and an executive session that may cover items 12 through 19. [25]

    • Pending

      As of October 14, 2026 no minutes or news report of actions taken at the October 14 CRMWA board meeting had been located. [25]

  21. Scheduled

    Expected: CRMWA issues debt to build CRMWA II (MOU target 2034)

    Under the MOU's timeline, CRMWA would issue debt to construct CRMWA II in 2034, with construction estimated at about four years. The MOU states that each member city's council is required to approve CRMWA's debt issuances.[2][11]

    Canadian River Municipal Water Authority (CRMWA)

    • Pending

      Projection: the MOU's timeline would require CRMWA to issue debt to construct CRMWA II in 2034; the rate consultant likewise anticipated additional debt for CRMWA II in 2034. Under the MOU, each member city council, including Amarillo's, must approve CRMWA debt issuances. The MOU is non-binding and states plans could change with drought, infrastructure conditions or demand.[2][11]

  22. Scheduled

    Expected: CRMWA II operational by the end of 2038 (MOU target)

    The MOU states the parties' agreement, as of January 2026, that CRMWA II should be operational by the end of 2038. Other sources give different target years. The MOU remains in effect until CRMWA II is operational.[2][21][12]

    Canadian River Municipal Water Authority (CRMWA)

    • ⚠ Sources differ

      Sources give different target dates for CRMWA II to be in service.

      Reported value 1[2][1][21]

      Year
      2,038

      MOU (as of January 2026): operational by the end of 2038; also CRMWA's history page and NewsChannel 10

      Reported value 2[12]

      Year
      2,040

      2026 Panhandle Water Plan: CRMWA's ASR supply available "after CRMWA II is online in 2040"

      Reported value 3[11]

      Year
      2033-34

      Rate consultant Chris Ekrut (April 14, 2026), as reported: future CRMWA water supply anticipated around 2033-34

      Reported value 4[20]

      Years to complete
      8

      CRMWA general manager (June 23, 2026): about eight years to complete if all member cities approve

Related storylines: Amarillo's wastewater plants: failures, enforcement, expansion financing and rate increases (2022-2026)City of Amarillo water supply agreement with Fermi America (2025-2026)Osage Water Treatment Plant: filter, basin and chlorine rehabilitation (2001-2026)